In problem, how much will be produced in each of the 3 months?
problem
A company wants to produce 500 units over the next 3 months at a uniform rate. The months have 19, 20, and 21 working days, respectively. On the average, how much should the company produce each day to level production?
problem
A company wants to produce 500 units over the next 3 months at a uniform rate. The months have 19, 20, and 21 working days, respectively. On the average, how much should the company produce each day to level production?
التوضيح
Production leveling:
Production levelin...