Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for 100 As to be available in week 5. There are 20 Bs available. All other on-hand balances = 0.



التوضيح
Determine gross and net requirement :
Th...