expand icon
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

النسخة 8الرقم المعياري الدولي: 978-0134156323
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

النسخة 8الرقم المعياري الدولي: 978-0134156323
تمرين 7
Complete the following table. Lead time for the part is 2 weeks. The lot size is 50.What is the projected available at the end of week 3? When is it planned to release an order? Complete the following table. Lead time for the part is 2 weeks. The lot size is 50.What is the projected available at the end of week 3? When is it planned to release an order?
التوضيح
موثّق
like image
like image

Calculate projected available at the end...