expand icon
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

النسخة 8الرقم المعياري الدولي: 978-0134156323
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

النسخة 8الرقم المعياري الدولي: 978-0134156323
تمرين 9
MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets. MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets.      MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets.      MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets.
التوضيح
موثّق
like image
like image

Material Requirements Planning (MRP) is ...

close menu
Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive
cross icon