تمرين 11
How many standard hours are needed to run an order of 200 pieces if the setup time is 1.3 hours and the run time 0.3 hours per piece? How many actual hours are needed at the work center if the efficiency is 130% and the utilization is 70%?
التوضيح
موثّق
like image
like image

Calculate standard hours required to run...