Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive
النسخة 8الرقم المعياري الدولي: 978-0134156323
Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive
النسخة 8الرقم المعياري الدولي: 978-0134156323 تمرين 17
Back schedule the following shop order. All times are given in days. Move time between operations is 1 day, and wait time is 1 day. Due date is day 150. Assume orders start at the beginning of a day and finish at the end of a day. 

التوضيح
Back scheduling is the normal process th...