What is the critical path in the PERT method for network analysis?
A) shortest path through the network
B) longest path through the network
C) path with the most slack
D) path with the most variability in estimated times
E) least cost path
A) shortest path through the network
B) longest path through the network
C) path with the most slack
D) path with the most variability in estimated times
E) least cost path