تمرين 9
What is the efficiency of an assembly line that has 25 workers and a cycle time of 45 seconds? Each unit produced on the line has 16 minutes of work that needs to be completed based on a time study completed by engineers at the factory.
التوضيح
موثّق
like image
like image

A layout, in which the jobs are arranged...