The PERT is combined with cost data to produce a PERT cost analysis to
A) calculate the total project cost inclusive of the additional slack time.
B) evaluate and optimize trade-offs between time of an event's completion and its cost to complete.
C) implement computer-integrated manufacturing concepts.
D) avoid the problem of time variance analysis.
E) calculate expected activity times.
A) calculate the total project cost inclusive of the additional slack time.
B) evaluate and optimize trade-offs between time of an event's completion and its cost to complete.
C) implement computer-integrated manufacturing concepts.
D) avoid the problem of time variance analysis.
E) calculate expected activity times.
التوضيح
• Project Evaluation and Review Techniqu...