
Accounting Information Systems 8th Edition by James Hall
النسخة 8الرقم المعياري الدولي: 978-1111972141
Accounting Information Systems 8th Edition by James Hall
النسخة 8الرقم المعياري الدولي: 978-1111972141 تمرين 55
What is the critical path in the PERT method for network analysis?
A) shortest path through the network
B) longest path through the network
C) path with the most slack
D) path with the most variability in estimated times
E) least cost path
A) shortest path through the network
B) longest path through the network
C) path with the most slack
D) path with the most variability in estimated times
E) least cost path
التوضيح
• Project Evaluation and Review Techniqu...
Accounting Information Systems 8th Edition by James Hall
لماذا لم يعجبك هذا التمرين؟
أخرى 8 أحرف كحد أدنى و 255 حرفاً كحد أقصى
حرف 255

