Cornerstones of Cost Accounting 1st Edition by Don Hansen,Maryanne Mowen
النسخة 1الرقم المعياري الدولي: 978-0538736787
Cornerstones of Cost Accounting 1st Edition by Don Hansen,Maryanne Mowen
النسخة 1الرقم المعياري الدولي: 978-0538736787 تمرين 28
STANDARD COSTS, DECOMPOSITION OF BUDGET VARIANCES, DIRECT MATERIALS AND DIRECT LABOR
Brookford Corporation produces dress shirts. The company uses a standard costing system and has set the following standards for direct materials and direct labor (for one shirt):
During the year, Brookford produced 6,800 shirts. The actual fabric purchased was 10,750 yards at $2.30 per yard. There were no beginning or ending inventories of fabric. Actual direct labor was 6,850 hours at $12.25 per hour.
Required:
1. Compute the costs of fabric and direct labor that should have been incurred for the production of 6,800 shirts.
2. Compute the total budget variances for direct materials and direct labor.
3. Break down the total budget variance for direct materials into a price variance and a usage variance. Prepare the journal entries associated with these variances.
4. Break down the total budget variance for direct labor into a rate variance and an efficiency variance. Prepare the journal entries associated with these variances.
Brookford Corporation produces dress shirts. The company uses a standard costing system and has set the following standards for direct materials and direct labor (for one shirt):
During the year, Brookford produced 6,800 shirts. The actual fabric purchased was 10,750 yards at $2.30 per yard. There were no beginning or ending inventories of fabric. Actual direct labor was 6,850 hours at $12.25 per hour.
Required:
1. Compute the costs of fabric and direct labor that should have been incurred for the production of 6,800 shirts.
2. Compute the total budget variances for direct materials and direct labor.
3. Break down the total budget variance for direct materials into a price variance and a usage variance. Prepare the journal entries associated with these variances.
4. Break down the total budget variance for direct labor into a rate variance and an efficiency variance. Prepare the journal entries associated with these variances.
التوضيح
1.
Cost of direct materials - standard ...