
Cornerstones of Managerial Accounting 6th Edition by Maryanne Mowen,Don Hansen ,Dan Heitger
النسخة 6الرقم المعياري الدولي: 978-1305103962
Cornerstones of Managerial Accounting 6th Edition by Maryanne Mowen,Don Hansen ,Dan Heitger
النسخة 6الرقم المعياري الدولي: 978-1305103962 تمرين 9
( Appendix 12A ) Cycle Time and Velocity
Lasker Company divided its tool production factory into manufacturing cells. Each cell produces one product. The cordless drill cell had the following data for last quarter:
Maximum units produced in a quarter: 90,000 units
Actual units produced in a quarter: 75,000 units
Hours of cell production labor in a quarter: 30,000 hours
Required:
Compute the (1) theoretical cycle time (in minutes), (2) actual cycle time (in minutes), (3) theoretical velocity (in units per hour), and (4) actual velocity (in units per hour).
Lasker Company divided its tool production factory into manufacturing cells. Each cell produces one product. The cordless drill cell had the following data for last quarter:
Maximum units produced in a quarter: 90,000 units
Actual units produced in a quarter: 75,000 units
Hours of cell production labor in a quarter: 30,000 hours
Required:
Compute the (1) theoretical cycle time (in minutes), (2) actual cycle time (in minutes), (3) theoretical velocity (in units per hour), and (4) actual velocity (in units per hour).
التوضيح
Variance analysis: It is the examination...
Cornerstones of Managerial Accounting 6th Edition by Maryanne Mowen,Don Hansen ,Dan Heitger
لماذا لم يعجبك هذا التمرين؟
أخرى 8 أحرف كحد أدنى و 255 حرفاً كحد أقصى
حرف 255

