Cornerstones of Cost Management 2nd Edition by Don Hansen ,Maryanne Mowen
النسخة 2الرقم المعياري الدولي: 978-1111824402
Cornerstones of Cost Management 2nd Edition by Don Hansen ,Maryanne Mowen
النسخة 2الرقم المعياري الدولي: 978-1111824402 تمرين 13
(2009 CPA Exam, adapted)
Merry Co. has two major categories of factory overhead: material handling and quality control. The costs expected for these categories for the coming year are:
The plant currently applies overhead based on direct labor hours. The estimated direct labor hours are 80,000 per year. The plant manager is asked to submit a bid and assembles the following data on a proposed job:
What amount is the estimated product cost on the proposed job?
a. $8,000
b. $10,000
c. $14,000
d. $18,000
Merry Co. has two major categories of factory overhead: material handling and quality control. The costs expected for these categories for the coming year are:
The plant currently applies overhead based on direct labor hours. The estimated direct labor hours are 80,000 per year. The plant manager is asked to submit a bid and assembles the following data on a proposed job:
What amount is the estimated product cost on the proposed job?
a. $8,000
b. $10,000
c. $14,000
d. $18,000
التوضيح
The overhead costs of Merry Co. are ment...
Cornerstones of Cost Management 2nd Edition by Don Hansen ,Maryanne Mowen
لماذا لم يعجبك هذا التمرين؟
أخرى 8 أحرف كحد أدنى و 255 حرفاً كحد أقصى
حرف 255