تمرين 54
Flexible Budget for Varying Levels of Activity
Refer to Cornerstone Exercise 8.13. In March, Nashler Company produced 163,200 units and had the following actual costs:
Flexible Budget for Varying Levels of Activity  Refer to Cornerstone Exercise 8.13. In March, Nashler Company produced 163,200 units and had the following actual costs:     Required:  1. Prepare a performance report for Nashler Company comparing actual costs with the flexible budget for actual units produced. 2. What if Nashler Company's actual direct materials cost were $1,175,040? How would that affect the variance for direct materials? The total cost variance?
Required:
1. Prepare a performance report for Nashler Company comparing actual costs with the flexible budget for actual units produced.
2. What if Nashler Company's actual direct materials cost were $1,175,040? How would that affect the variance for direct materials? The total cost variance?
التوضيح
موثّق
like image
like image

The information on the actual cost incur...