The critical path in a PERT chart represents: a. The sequencing of tasks
B) The most important tasks of the whole project
C) The longest path of tasks needed for project completion
D) The tasks that must be completed without errors
B) The most important tasks of the whole project
C) The longest path of tasks needed for project completion
D) The tasks that must be completed without errors
التوضيح
a.
The sequencing o f tasks : PERT is th...