expand icon
book Introduction to Management Science 12th Edition by Bernard Taylor cover

Introduction to Management Science 12th Edition by Bernard Taylor

النسخة 12الرقم المعياري الدولي: 978-0133778847
book Introduction to Management Science 12th Edition by Bernard Taylor cover

Introduction to Management Science 12th Edition by Bernard Taylor

النسخة 12الرقم المعياري الدولي: 978-0133778847
تمرين 13
For the network in Problem, determine the earliest and latest activity times and the slack for each activity. Indicate how the critical path would be determined from this information.
Problem
Identify all the paths in the following network, compute the length of each, and indicate the Critical path (activity times are in weeks):
التوضيح
موثّق
like image
like image

Consider the following activity network ...

close menu
Introduction to Management Science 12th Edition by Bernard Taylor
cross icon