The Dynaco Manufacturing Company has an assembly line that feeds two drill presses. As partially completed products come off the line, they are lined up to be worked on as drill presses become available. The units arrive at the workstation (containing both presses) at the rate of 100 per hour. Each press operator can process an average of 60 units per hour. Compute L , L q , W , and W q.
التوضيح
موثّق
like image
like image

The available data to solve the problem ...