Service Management 7th Edition by James Fitzsimmons, Mona Fitzsimmons
النسخة 7الرقم المعياري الدولي: 9780071289276
Service Management 7th Edition by James Fitzsimmons, Mona Fitzsimmons
النسخة 7الرقم المعياري الدولي: 9780071289276 تمرين 1
A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified:
a. Draw a project network diagram.
b. Calculate the scheduling times and total slack for each activity.
c. List the critical path activities and project duration.
d. Assuming that one worker is required for each activity, prepare a resource-leveled schedule. What is the maximum number of workers required to finish the project on time?

a. Draw a project network diagram.
b. Calculate the scheduling times and total slack for each activity.
c. List the critical path activities and project duration.
d. Assuming that one worker is required for each activity, prepare a resource-leveled schedule. What is the maximum number of workers required to finish the project on time?
التوضيح
PERT and CPM:
In order to keep track of...