The following activities have been identified by a consulting firm that is developing an information system for an insurance firm to make a transition to a "paperless" organization:
a. Draw the project network showing the activities with their expected times.
b. What is the critical path and the expected duration of the project?
c. What is the probability of completing the project within 2 years?
a. Draw the project network showing the activities with their expected times.
b. What is the critical path and the expected duration of the project?
c. What is the probability of completing the project within 2 years?
التوضيح
PERT and CPM:
In order to keep track of...