The project network and table below show the expected number of weeks to complete a series of activities and the corresponding variances:
a. Determine the critical path and the earliest expected completion time.
b. What is the probability of completing the project in 24 weeks or less?
a. Determine the critical path and the earliest expected completion time.
b. What is the probability of completing the project in 24 weeks or less?
التوضيح
(a) Critical Path Activities:...
Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi