You are in charge of developing a 48-KDSI organic-mode product that is nominal in every respect.
(i) Assuming a cost of $10,100 per person-month, how much is the project estimated to cost?
(ii) Your entire development team resigns at the start of the project. You are fortunate enough to be able to replace the nominal team with a very highly experienced and capable team, but the cost per person-month will rise to $13,400. How much money do you expect to gain (or lose) as a result of the personnel change?
(i) Assuming a cost of $10,100 per person-month, how much is the project estimated to cost?
(ii) Your entire development team resigns at the start of the project. You are fortunate enough to be able to replace the nominal team with a very highly experienced and capable team, but the cost per person-month will rise to $13,400. How much money do you expect to gain (or lose) as a result of the personnel change?
التوضيح
The data given in the problem is as foll...