expand icon
book Business Law 12th Edition by Roger LeRoy Miller ,Frank Cross cover

Business Law 12th Edition by Roger LeRoy Miller ,Frank Cross

النسخة 12الرقم المعياري الدولي: 978-1111530594
book Business Law 12th Edition by Roger LeRoy Miller ,Frank Cross cover

Business Law 12th Edition by Roger LeRoy Miller ,Frank Cross

النسخة 12الرقم المعياري الدولي: 978-1111530594
تمرين 16
Liquidated Damages Cohen contracts to sell his house and lot to Windsor for $100,000. The terms of the contract call for Windsor to pay 10 percent of the purchase price as a deposit toward the purchase price, or a down payment. The terms further stipulate that if the buyer breaches the contract, Cohen will retain the deposit as liquidated damages. Windsor pays the deposit, but because her expected financing of the $90,000 balance falls through, she breaches the contract. Two weeks later Cohen sells the house and lot to Ballard for $105,000. Windsor demands her $10,000 back, but Cohen refuses, claiming that Windsor's breach and the contract terms entitle him to keep the deposit. Discuss who is correct.
التوضيح
موثّق
like image
like image

Liquidated Damages:
In the case of Wind...

close menu
Business Law 12th Edition by Roger LeRoy Miller ,Frank Cross
cross icon