Job Costing Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. For 2013, estimated direct labor-hours are 95,000 and estimated factory overhead is $617,500. The following information is for September 2013. Job A was completed during September, and Job B was started but not finished.
Required
1. What is the total cost of Job A
2. What is the total factory overhead applied during September
3. What is the overapplied or underapplied overhead for September
Required
1. What is the total cost of Job A
2. What is the total factory overhead applied during September
3. What is the overapplied or underapplied overhead for September
التوضيح
Overheads: It is the defined sum of the ...