Application of Overhead Tomek Company uses a job costing system that applies factory overhead on the basis of direct labor-hours. The company's factory overhead budget for 2013 included the following estimates:
Required
1. Compute the firm's predetermined factory overhead rate for 2013.
2. Calculate the amount of overapplied or underapplied overhead.
3. Prepare a journal entry to transfer the underapplied or overapplied overhead to the Cost of Goods Sold account.
Required
1. Compute the firm's predetermined factory overhead rate for 2013.
2. Calculate the amount of overapplied or underapplied overhead.
3. Prepare a journal entry to transfer the underapplied or overapplied overhead to the Cost of Goods Sold account.
التوضيح
Answer Sub Part (1)
The predetermined r...