In order to plan for procurements, the project team uses a project document that includes a list of deliverables, acceptance criteria, project assumptions and constraints, and a description of the product, service or result. This document is called the_______
A) work breakdown structure (WBS)
B) project charter
C) project contract
D) project scope statement
A) work breakdown structure (WBS)
B) project charter
C) project contract
D) project scope statement