expand icon
book Contemporary Project Management 3rd Edition by Timothy Kloppenborg cover

Contemporary Project Management 3rd Edition by Timothy Kloppenborg

النسخة 3الرقم المعياري الدولي: 978-1285433356
book Contemporary Project Management 3rd Edition by Timothy Kloppenborg cover

Contemporary Project Management 3rd Edition by Timothy Kloppenborg

النسخة 3الرقم المعياري الدولي: 978-1285433356
تمرين 2
In order to plan for procurements, the project team uses a project document that includes a list of deliverables, acceptance criteria, project assumptions and constraints, and a description of the product, service or result. This document is called the_______
A) work breakdown structure (WBS)
B) project charter
C) project contract
D) project scope statement
التوضيح
موثّق
like image
like image

In order to plan for procurements, the p...

close menu
Contemporary Project Management 3rd Edition by Timothy Kloppenborg
cross icon