Procurement performance reviews, contract change control system, payment systems, and performance reporting are all tools and techniques for which procurement process?
A) Plan procurement management
B) Conduct procurements
C) Close procurements
D) Control procurements
A) Plan procurement management
B) Conduct procurements
C) Close procurements
D) Control procurements
التوضيح
Project procurement management process i...