Juan is a project manager for a project that has been baselined and is now underway. When a customer approaches Juan and asks him to increase the project ' s scope, Juan ' s response should be to ________.
A) comply with the customer ' s request if it seems reasonable
B) determine the schedule performance index (SPI)
C) perform integrated change control
D) calculate the Estimate to Complete (ETC)
A) comply with the customer ' s request if it seems reasonable
B) determine the schedule performance index (SPI)
C) perform integrated change control
D) calculate the Estimate to Complete (ETC)
التوضيح
J should not increase in the project sco...