________ is the " process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks and evaluating risk process effectiveness throughout the project."
A) Issue management
B) Change control
C) Control risks
D) Preventive action
A) Issue management
B) Change control
C) Control risks
D) Preventive action