Good project management practice suggests a need to include a ________ within the cost baseline in order to cover identified risks that are accepted, and for which responses have been developed.
A) contingency reserve
B) project buffer
C) control account
D) management reserve
A) contingency reserve
B) project buffer
C) control account
D) management reserve
التوضيح
The project team in planning may recogni...