تمرين 51
( Appendix 12A ) Calculating Manufacturing Cycle Efficiency
Indy Company has the following data for one of its manufacturing plants:
Maximum units produced in a quarter (3-month period): 250,000 units
Actual units produced in a quarter (3-month period): 200,000 units
Productive hours in one quarter: 25,000 hours
Refer to the information for Indy Company above. The actual cycle time for Indy Company is 7.5 minutes and the theoretical cycle time is 6 minutes.
Required:
1. Calculate the amount of processing time and the amount of nonprocessing time.
2. Calculate the MCE.
التوضيح
موثّق
like image
like image

• Cycle time is the length of time it ta...