تمرين 50
Consider the cash flow series given. In computing the equivalent worth at n = 4, which of the following equations is incorrect
(a) V 4 = [$100( P / A , / ,6)
$100( P / F , i ,4)]( F / P , i ,4)
(b) V 4 = $100( F / A , i ,3) +
$100( P / A , i ,2)
(c) V 4 = $100( F / A , i ,4) $100 +
$100( P / A , Z , 2)
(d) V 4 = [$100( F / A , i , 6)
$100( F / P , i ,2)]( P / F , i ,2)
Figure P3.64
Consider the cash flow series given. In computing the equivalent worth at n = 4, which of the following equations is incorrect  (a) V 4 = [$100( P / A , / ,6)  $100( P / F , i ,4)]( F / P , i ,4) (b) V 4 = $100( F / A , i ,3) + $100( P / A , i ,2) (c) V 4 = $100( F / A , i ,4) $100 + $100( P / A , Z , 2) (d) V 4 = [$100( F / A , i , 6)  $100( F / P , i ,2)]( P / F , i ,2) Figure P3.64