expand icon
book Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender cover

Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender

النسخة 2الرقم المعياري الدولي: 978-0072328882
book Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender cover

Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender

النسخة 2الرقم المعياري الدولي: 978-0072328882
تمرين 4
Usually each of the three principal parties (the owner, designer, and contractor) prepares a cost estimate at different times during the life of a project. Describe the purpose of each estimate and the impact that estimating errors may have on the other two parties.
التوضيح
موثّق
like image
like image

Owner's Estimate:
- Itis typically dev...