expand icon
book Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender cover

Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender

النسخة 2الرقم المعياري الدولي: 978-0072328882
book Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender cover

Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender

النسخة 2الرقم المعياري الدولي: 978-0072328882
تمرين 7
Use the time and location indices in Example 5-2 to estimate the cost of a building that contains 64,500 square feet or floor area. The building is to be constructed two years from now in city A. The cost of a similar type building that contains 95,000 square feet was completed last year in city C for a cost of $7,790,000.
التوضيح
موثّق
like image
like image

Estimated Cost = Previous Cost x Adjustm...

close menu
Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender
cross icon