Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender
النسخة 2الرقم المعياري الدولي: 978-0072328882
Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender
النسخة 2الرقم المعياري الدولي: 978-0072328882 تمرين 9
The development of a work plan for a project follows four phases: project definition, framework, schedule, and tracking. Identify and briefly describe the parts that make up each of these four phases.
التوضيح
Project Definition:
- Owner's feasibil...