An assembly line currently has five workstations and the time required for each is shown below.
a.What is the current cycle time?
b.What is the efficiency of the process?
c.Customer demand is 80 units per hour.What is the hourly production rate of the current process?
d.?What does the cycle time need to be to be able to meet demand (what is the takt time)?
e.What changes to the process are needed?
a.What is the current cycle time?
b.What is the efficiency of the process?
c.Customer demand is 80 units per hour.What is the hourly production rate of the current process?
d.?What does the cycle time need to be to be able to meet demand (what is the takt time)?
e.What changes to the process are needed?
التوضيح
The overall cycle time of an assembly li...