Given the following information about a small project,
a.Draw a network diagram.
b.Identify the critical path, earliest start and finish and slack for each task.
c.Which of these activities should the project manager track most closely?
d.What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?
a.Draw a network diagram.b.Identify the critical path, earliest start and finish and slack for each task.
c.Which of these activities should the project manager track most closely?
d.What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?
التوضيح
Given data:
(b)Standard definition def...