expand icon
book Cost Management: A Strategic Emphasis 7th Edition by Edward Blocher,David Stout ,Paul Juras,Gary Cokins cover

Cost Management: A Strategic Emphasis 7th Edition by Edward Blocher,David Stout ,Paul Juras,Gary Cokins

النسخة 7الرقم المعياري الدولي: 978-0077733773
book Cost Management: A Strategic Emphasis 7th Edition by Edward Blocher,David Stout ,Paul Juras,Gary Cokins cover

Cost Management: A Strategic Emphasis 7th Edition by Edward Blocher,David Stout ,Paul Juras,Gary Cokins

النسخة 7الرقم المعياري الدولي: 978-0077733773
تمرين 24
A customer places an order on January 1, 2016. Ten days later that order is received by the manufacturing department. Fifteen days later, the order is put into production. Processing (manufacturing) time is 20 days for this order. The completed order is then shipped 10 days later. For this order, what was the total customer-response time (CRT)
التوضيح
موثّق
like image
like image

Customer response time:
The time lapse ...