expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
تمرين 21
Consider the following project network and activity times (in weeks): Consider the following project network and activity times (in weeks):      a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? e. What is the schedule for activity E? Consider the following project network and activity times (in weeks):      a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? e. What is the schedule for activity E?
a. Identify the critical path.
b. How much time will be needed to complete this project?
c. Can activity D be delayed without delaying the entire project? If so, by how many weeks?
d. Can activity C be delayed without delaying the entire project? If so, by how many weeks?
e. What is the schedule for activity E?
التوضيح
موثّق
like image
like image

a)Identify the critical path in the netw...