The following estimates of activity times (in days) are available for a small project:
a. Compute the expected activity completion times and the variance for each activity.
b. An analyst determine that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance.

a. Compute the expected activity completion times and the variance for each activity.
b. An analyst determine that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance.
التوضيح
a)Compute the expected activity completi...