expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
تمرين 5
Assume that the activity time estimates (in days for the swimming pool construction project in Problem 11 are as follows: Assume that the activity time estimates (in days for the swimming pool construction project in Problem 11 are as follows:    a. What are the critical activities? b. What is the expected time to complete the project? c. What is the probability that the project can be completed in 25 or fewer days?
a. What are the critical activities?
b. What is the expected time to complete the project?
c. What is the probability that the project can be completed in 25 or fewer days?
التوضيح
موثّق
like image
like image

a)Compute the expected activity completi...