Suppose that the following estimates of activity times (in weeks) were provided for the network shown in Problem 6:
What is the probability that the project will be completed
a. Within 21 weeks?
b. Within 22 weeks?
c. Within 25 weeks?

What is the probability that the project will be completed
a. Within 21 weeks?
b. Within 22 weeks?
c. Within 25 weeks?
التوضيح
a)For computing the probability that the...