expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
تمرين 20
Consider the following project network and activity times (in days): Consider the following project network and activity times (in days):      The crashing data for this project are as follows:    a. Find the critical path and the expected project completion time. b. What is the total project cost using the normal times? Consider the following project network and activity times (in days):      The crashing data for this project are as follows:    a. Find the critical path and the expected project completion time. b. What is the total project cost using the normal times?
The crashing data for this project are as follows: Consider the following project network and activity times (in days):      The crashing data for this project are as follows:    a. Find the critical path and the expected project completion time. b. What is the total project cost using the normal times?
a. Find the critical path and the expected project completion time.
b. What is the total project cost using the normal times?
التوضيح
موثّق
like image
like image

a)To find the critical path and activity...

close menu
An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin
cross icon