Refer to Problem 21. Assume that management desires a 12-day project completion time.
a. Formulate a linear programming model that can be used to assist with the crashing decisions.
b. What activities should be crashed?
c. What is the total project cost for the 12-day completion time?
a. Formulate a linear programming model that can be used to assist with the crashing decisions.
b. What activities should be crashed?
c. What is the total project cost for the 12-day completion time?
التوضيح
a)Formulate a linear programming model a...