expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

النسخة 13الرقم المعياري الدولي: 978-1439043271
تمرين 22
Refer to Problem 21. Assume that management desires a 12-day project completion time.
a. Formulate a linear programming model that can be used to assist with the crashing decisions.
b. What activities should be crashed?
c. What is the total project cost for the 12-day completion time?
التوضيح
موثّق
like image
like image

a)Formulate a linear programming model a...

close menu
An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin
cross icon