Deck 11: Project Management

Full screen (f)
exit full mode
Question
Both PERT and CPM networks show activities and activity sequences.
Use Space or
up arrow
down arrow
to flip the card.
Question
The three time estimates employed in PERT are optimistic time,average time,and pessimistic time.
Question
CPM was developed for use in managing projects about which we have good information about activity or task completion times.
Question
CPM is a probabilistic analysis of managing a project.
Question
The first step in planning and scheduling a project is to develop the work breakdown structure.
Question
The expected completion time and variance of an activity is approximated by the normal distribution in a PERT analysis.
Question
With CPM,we are able to calculate the probability of finishing the project within a specified time.
Question
Before drawing a PERT or CPM network,we must identify all activities and their predecessors.
Question
In PERT,the most likely completion time of an activity is used to represent that activity's time within a project.
Question
The identification of the project activities and their time,cost,resource requirements,predecessors,and person(s)responsible is called PERT planning.
Question
PERT is a network technique similar to CPM,but PERT allows for project crashing,whereas CPM does not.
Question
In PERT,the earliest start time for an activity is equal to the latest of the earliest finish times of all of its immediate predecessors.
Question
The optimistic time is the greatest amount of time that could be required to complete an activity.
Question
With PERT,we are able to calculate the probability of finishing the project within a specified time.
Question
PERT had its beginnings in a military department of the United States.
Question
PERT is a deterministic analysis tool allowing for precise times of activities within a project.
Question
Given the variability of the activity completion times,the original critical path we identify in our PERT analysis may not always be the actual critical path as the project takes place.
Question
A PERT/CPM network is a graphical display of a project that connects activities.
Question
PERT was developed for a project for which activity or task times were uncertain.
Question
PERT and CPM are quantitative analysis tools designed to schedule and control large projects.
Question
Given the assumptions in PERT,the probability that a project will be completed in less time than required by the activities on the critical path is approximately 50%.
Question
Gantt charts contain information about the time taken by each activity,but not about the sequential dependencies of the activities.
Question
One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail-and thus come to an understanding of relationships between the activities.
Question
The critical path of a network is the

A)shortest time path through the network.
B)path with the fewest activities.
C)path with the most activities.
D)longest time path through the network.
E)None of the above
Question
Gantt charts and PERT diagrams provide the same information,just in different formats.
Question
Through the use of PERT/CPM,astute managers can derive flexibility by identifying noncritical activities and replanning,rescheduling,and reallocating resources such as personnel and finances.
Question
Budgets are computed using only ES times.
Question
PERT stands for Probabilistic Evaluation and Review Technique.
Question
In PERT,we assume that the project completion time can be modeled by the normal distribution.
Question
The longest time path through a PERT/CPM network is called the critical path.
Question
One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an activity.
Question
Shortening a project is called crashing.
Question
The value of work completed is computed by multiplying budgeted cost by the percent completion.
Question
In PERT,the variance in completion time is equal to the variance of the most time consuming activity on the critical path.
Question
The activity crash cost is equal to the incremental cost of shortening the project.
Question
In a PERT network,the earliest (activity)start time is the

A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
E)None of the above
Question
In CPM,crashing an activity that is not on the critical path increases the cost of the project.
Question
Slack is the time an activity can be delayed without impacting the completion time of the project.
Question
CPM stands for Comprehensive Project Method.
Question
The variance of the project completion time is equal to the sum of the variances of all the activities.
Question
Given an activity's optimistic,most likely,and pessimistic time estimates of 4,6,and 14 days respectively,compute the PERT expected activity time for this activity.

A)8
B)6
C)7
D)9
E)None of the above
Question
Given an activity's optimistic,most likely,and pessimistic time estimates of 4,12,and 18 days respectively,compute the PERT variance for this activity.

A)2.33
B)5.44
C)8.00
D)64.00
E)None of the above
Question
The expected time in PERT is

A)a weighted average of the most optimistic time,most pessimistic time,and four times the most likely time.
B)the modal time of a beta distribution.
C)a simple average of the most optimistic,most likely,and most pessimistic times.
D)the square root of the sum of the variances of the activities on the critical path.
E)None of the above
Question
PERT

A)assumes that we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a network technique that uses three time estimates for each activity in a project.
D)is a deterministic network technique that allows for project crashing.
E)None of the above
Question
Slack time in a network is the

A)amount of time that an activity would take assuming very unfavorable conditions.
B)shortest amount of time that could be required to complete the activity.
C)amount of time that you would expect it would take to complete the activity.
D)difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.
E)amount of time that an activity can be delayed without delaying the entire project.
Question
Given an activity's optimistic,most likely,and pessimistic time estimates of 2,10,and 20 days respectively,compute the PERT variance for this activity.

A)3
B)6
C)9
D)18
E)None of the above
Question
Given the following small project,the critical path is ________ days. <strong>Given the following small project,the critical path is ________ days.  </strong> A)10 B)14 C)16 D)20 E)None of the above <div style=padding-top: 35px>

A)10
B)14
C)16
D)20
E)None of the above
Question
According to Table 11-1,compute the slack time for activity D.

A)0
B)5
C)3
D)6
E)None of the above
Question
Managers use the network analysis of PERT and CPM to help them

A)derive flexibility by identifying noncritical activities.
B)replan,reschedule,and reallocate resources such as manpower and finances.
C)plan,schedule,monitor,and control large and complex projects.
D)All of the above
E)None of the above
Question
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 15 days,respectively,compute the PERT standard deviation for this activity.

A)2
B)4
C)5
D)15
E)None of the above
Question
Given an activity's optimistic,most likely,and pessimistic time estimates of 4,14,and 18 days respectively,compute the PERT expected activity time for this activity.

A)14
B)12
C)11
D)13
E)None of the above
Question
Table 11-1
The following represents a project with known activity times.All times are in weeks. <strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1,what is the minimum possible time required for completing the project?</strong> A)8 B)14 C)25 D)10 E)None of the above <div style=padding-top: 35px>
Using the data in Table 11-1,what is the minimum possible time required for completing the project?

A)8
B)14
C)25
D)10
E)None of the above
Question
Given the following small project,the critical path is ________ days. <strong>Given the following small project,the critical path is ________ days.  </strong> A)4 B)10 C)12 D)22 E)None of the above <div style=padding-top: 35px>

A)4
B)10
C)12
D)22
E)None of the above
Question
Which of the following is not a concept associated with CPM?

A)normal time
B)probability
C)normal cost
D)crash cost
E)deterministic network
Question
The first step in planning and scheduling a project is to develop the

A)employee scheduling plan.
B)PERT/CPM network diagram.
C)critical path.
D)work breakdown structure.
E)variance calculations for each activity.
Question
Table 11-2
The following represents a project with four activities.All times are in weeks. <strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to the data in Table 11-2,what is the critical path?</strong> A)A-B B)A-C C)B-D D)A-B-C-D E)None of the above <div style=padding-top: 35px>
According to the data in Table 11-2,what is the critical path?

A)A-B
B)A-C
C)B-D
D)A-B-C-D
E)None of the above
Question
Given an activity's optimistic,most likely,and pessimistic time estimates of 2,5,and 14 days respectively,compute the PERT expected activity time for this activity.

A)6
B)7
C)9
D)5
E)None of the above
Question
Table 11-1
The following represents a project with known activity times.All times are in weeks. <strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1,what is the latest possible time that C may be started without delaying completion of the project?</strong> A)0 B)4 C)8 D)10 E)None of the above <div style=padding-top: 35px>
Using the data in Table 11-1,what is the latest possible time that C may be started without delaying completion of the project?

A)0
B)4
C)8
D)10
E)None of the above
Question
Using the data in Table 11-1,compute the latest finish time for activity E.

A)4
B)10
C)14
D)25
E)None of the above
Question
CPM

A)assumes we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a deterministic network technique that allows for project crashing.
D)is a network technique that allows three time estimates for each activity in a project.
E)None of the above
Question
Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals. )

A)0.98
B)0.48
C)0.50
D)0.02
E)0.63
Question
Table 11-2
The following represents a project with four activities.All times are in weeks. <strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer,it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?</strong> A)2 B)4 C)8 D)12 E)None of the above <div style=padding-top: 35px>
According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer,it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?

A)2
B)4
C)8
D)12
E)None of the above
Question
Table 11-3 <strong>Table 11-3   According to Table 11-3,there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer,what mean and variance would be used?</strong> A)20 and 4.222 B)30 and 5.222 C)20 and 5.222 D)30 and 4.222 E)22.667 and 1.111 <div style=padding-top: 35px>
According to Table 11-3,there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer,what mean and variance would be used?

A)20 and 4.222
B)30 and 5.222
C)20 and 5.222
D)30 and 4.222
E)22.667 and 1.111
Question
The critical path of a network is the

A)path with the least variance.
B)path with zero slack.
C)path with the most activities.
D)path with the largest variance.
E)None of the above
Question
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?

A)108.0
B)110.4
C)89.6
D)85.0
E)100
Question
Table 11-3 <strong>Table 11-3   According to Table 11-3,there are five activities in a PERT project.What is the variance of the critical path?</strong> A)5.222 B)4.222 C)1.222 D)0 E)1.111 <div style=padding-top: 35px>
According to Table 11-3,there are five activities in a PERT project.What is the variance of the critical path?

A)5.222
B)4.222
C)1.222
D)0
E)1.111
Question
Table 11-2
The following represents a project with four activities.All times are in weeks. <strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals. )</strong> A)0.07 B)0.93 C)0.43 D)0.77 E)None of the above <div style=padding-top: 35px>
According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals. )

A)0.07
B)0.93
C)0.43
D)0.77
E)None of the above
Question
CPM stands for

A)critical path management.
B)critical project management.
C)critical project method.
D)critical path method.
E)centralized project management.
Question
The two common techniques for drawing PERT networks are

A)NOA and NRA.
B)AON and AOA.
C)GANTT and NOA.
D)ONA and OAO.
E)CAN and CAA.
Question
In a PERT network,the latest (activity)start time is the

A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
E)None of the above
Question
In PERT,we assume that

A)the times to complete individual activities are known with certainty.
B)all activities are carried out by staff from our own organization.
C)the total cost of a project is independent of the time to complete the project.
D)the total time to complete all activities on the critical path is described by a normal distribution.
E)None of the above
Question
Table 11-2
The following represents a project with four activities.All times are in weeks. <strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to the data in Table 11-2,what is the minimum expected completion time for the project?</strong> A)18 B)19 C)37 D)11 E)None of the above <div style=padding-top: 35px>
According to the data in Table 11-2,what is the minimum expected completion time for the project?

A)18
B)19
C)37
D)11
E)None of the above
Question
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 13 days respectively,compute the expected time for this activity.

A)3
B)4
C)5
D)6
E)None of the above
Question
PERT stands for

A)probabilistic evaluation and review technique.
B)program evaluation and review technique.
C)probability of expected run times.
D)program of expected run times.
E)project evaluation and review technique.
Question
Which of the following questions can be answered by PERT?

A)When will the entire project be completed?
B)What is the probability that the project will be completed by a specific date?
C)What are the critical activities?
D)What are the noncritical activities?
E)All of the above
Question
The work breakdown structure involves identifying the ________ for each activity.

A)time
B)cost
C)resource requirements
D)predecessors
E)All of the above
Question
Table 11-3 <strong>Table 11-3   According to Table 11-3,there are five activities in a PERT project.Which activities are on the critical path?</strong> A)A-B-C-D-E B)A-C-E C)B-D D)A-B-C-D E)B-E <div style=padding-top: 35px>
According to Table 11-3,there are five activities in a PERT project.Which activities are on the critical path?

A)A-B-C-D-E
B)A-C-E
C)B-D
D)A-B-C-D
E)B-E
Question
In PERT analysis,the probability of the optimistic time occurring should be on the order of

A)1/2.
B)1/3.
C)1/6.
D)1/10.
E)1/100.
Question
The expected time in PERT is

A)greater than the most likely time.
B)equal to the most likely time.
C)less than the most likely time.
D)Any of the above
E)None of the above
Question
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,7,and 11 days respectively,compute the expected time for this activity.

A)5
B)6
C)7
D)12
E)None of the above
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/134
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 11: Project Management
1
Both PERT and CPM networks show activities and activity sequences.
True
2
The three time estimates employed in PERT are optimistic time,average time,and pessimistic time.
False
3
CPM was developed for use in managing projects about which we have good information about activity or task completion times.
True
4
CPM is a probabilistic analysis of managing a project.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
5
The first step in planning and scheduling a project is to develop the work breakdown structure.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
6
The expected completion time and variance of an activity is approximated by the normal distribution in a PERT analysis.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
7
With CPM,we are able to calculate the probability of finishing the project within a specified time.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
8
Before drawing a PERT or CPM network,we must identify all activities and their predecessors.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
9
In PERT,the most likely completion time of an activity is used to represent that activity's time within a project.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
10
The identification of the project activities and their time,cost,resource requirements,predecessors,and person(s)responsible is called PERT planning.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
11
PERT is a network technique similar to CPM,but PERT allows for project crashing,whereas CPM does not.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
12
In PERT,the earliest start time for an activity is equal to the latest of the earliest finish times of all of its immediate predecessors.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
13
The optimistic time is the greatest amount of time that could be required to complete an activity.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
14
With PERT,we are able to calculate the probability of finishing the project within a specified time.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
15
PERT had its beginnings in a military department of the United States.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
16
PERT is a deterministic analysis tool allowing for precise times of activities within a project.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
17
Given the variability of the activity completion times,the original critical path we identify in our PERT analysis may not always be the actual critical path as the project takes place.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
18
A PERT/CPM network is a graphical display of a project that connects activities.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
19
PERT was developed for a project for which activity or task times were uncertain.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
20
PERT and CPM are quantitative analysis tools designed to schedule and control large projects.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
21
Given the assumptions in PERT,the probability that a project will be completed in less time than required by the activities on the critical path is approximately 50%.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
22
Gantt charts contain information about the time taken by each activity,but not about the sequential dependencies of the activities.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
23
One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail-and thus come to an understanding of relationships between the activities.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
24
The critical path of a network is the

A)shortest time path through the network.
B)path with the fewest activities.
C)path with the most activities.
D)longest time path through the network.
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
25
Gantt charts and PERT diagrams provide the same information,just in different formats.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
26
Through the use of PERT/CPM,astute managers can derive flexibility by identifying noncritical activities and replanning,rescheduling,and reallocating resources such as personnel and finances.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
27
Budgets are computed using only ES times.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
28
PERT stands for Probabilistic Evaluation and Review Technique.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
29
In PERT,we assume that the project completion time can be modeled by the normal distribution.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
30
The longest time path through a PERT/CPM network is called the critical path.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
31
One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an activity.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
32
Shortening a project is called crashing.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
33
The value of work completed is computed by multiplying budgeted cost by the percent completion.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
34
In PERT,the variance in completion time is equal to the variance of the most time consuming activity on the critical path.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
35
The activity crash cost is equal to the incremental cost of shortening the project.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
36
In a PERT network,the earliest (activity)start time is the

A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
37
In CPM,crashing an activity that is not on the critical path increases the cost of the project.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
38
Slack is the time an activity can be delayed without impacting the completion time of the project.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
39
CPM stands for Comprehensive Project Method.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
40
The variance of the project completion time is equal to the sum of the variances of all the activities.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
41
Given an activity's optimistic,most likely,and pessimistic time estimates of 4,6,and 14 days respectively,compute the PERT expected activity time for this activity.

A)8
B)6
C)7
D)9
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
42
Given an activity's optimistic,most likely,and pessimistic time estimates of 4,12,and 18 days respectively,compute the PERT variance for this activity.

A)2.33
B)5.44
C)8.00
D)64.00
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
43
The expected time in PERT is

A)a weighted average of the most optimistic time,most pessimistic time,and four times the most likely time.
B)the modal time of a beta distribution.
C)a simple average of the most optimistic,most likely,and most pessimistic times.
D)the square root of the sum of the variances of the activities on the critical path.
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
44
PERT

A)assumes that we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a network technique that uses three time estimates for each activity in a project.
D)is a deterministic network technique that allows for project crashing.
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
45
Slack time in a network is the

A)amount of time that an activity would take assuming very unfavorable conditions.
B)shortest amount of time that could be required to complete the activity.
C)amount of time that you would expect it would take to complete the activity.
D)difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.
E)amount of time that an activity can be delayed without delaying the entire project.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
46
Given an activity's optimistic,most likely,and pessimistic time estimates of 2,10,and 20 days respectively,compute the PERT variance for this activity.

A)3
B)6
C)9
D)18
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
47
Given the following small project,the critical path is ________ days. <strong>Given the following small project,the critical path is ________ days.  </strong> A)10 B)14 C)16 D)20 E)None of the above

A)10
B)14
C)16
D)20
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
48
According to Table 11-1,compute the slack time for activity D.

A)0
B)5
C)3
D)6
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
49
Managers use the network analysis of PERT and CPM to help them

A)derive flexibility by identifying noncritical activities.
B)replan,reschedule,and reallocate resources such as manpower and finances.
C)plan,schedule,monitor,and control large and complex projects.
D)All of the above
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
50
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 15 days,respectively,compute the PERT standard deviation for this activity.

A)2
B)4
C)5
D)15
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
51
Given an activity's optimistic,most likely,and pessimistic time estimates of 4,14,and 18 days respectively,compute the PERT expected activity time for this activity.

A)14
B)12
C)11
D)13
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
52
Table 11-1
The following represents a project with known activity times.All times are in weeks. <strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1,what is the minimum possible time required for completing the project?</strong> A)8 B)14 C)25 D)10 E)None of the above
Using the data in Table 11-1,what is the minimum possible time required for completing the project?

A)8
B)14
C)25
D)10
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
53
Given the following small project,the critical path is ________ days. <strong>Given the following small project,the critical path is ________ days.  </strong> A)4 B)10 C)12 D)22 E)None of the above

A)4
B)10
C)12
D)22
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
54
Which of the following is not a concept associated with CPM?

A)normal time
B)probability
C)normal cost
D)crash cost
E)deterministic network
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
55
The first step in planning and scheduling a project is to develop the

A)employee scheduling plan.
B)PERT/CPM network diagram.
C)critical path.
D)work breakdown structure.
E)variance calculations for each activity.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
56
Table 11-2
The following represents a project with four activities.All times are in weeks. <strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to the data in Table 11-2,what is the critical path?</strong> A)A-B B)A-C C)B-D D)A-B-C-D E)None of the above
According to the data in Table 11-2,what is the critical path?

A)A-B
B)A-C
C)B-D
D)A-B-C-D
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
57
Given an activity's optimistic,most likely,and pessimistic time estimates of 2,5,and 14 days respectively,compute the PERT expected activity time for this activity.

A)6
B)7
C)9
D)5
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
58
Table 11-1
The following represents a project with known activity times.All times are in weeks. <strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1,what is the latest possible time that C may be started without delaying completion of the project?</strong> A)0 B)4 C)8 D)10 E)None of the above
Using the data in Table 11-1,what is the latest possible time that C may be started without delaying completion of the project?

A)0
B)4
C)8
D)10
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
59
Using the data in Table 11-1,compute the latest finish time for activity E.

A)4
B)10
C)14
D)25
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
60
CPM

A)assumes we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a deterministic network technique that allows for project crashing.
D)is a network technique that allows three time estimates for each activity in a project.
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
61
Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals. )

A)0.98
B)0.48
C)0.50
D)0.02
E)0.63
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
62
Table 11-2
The following represents a project with four activities.All times are in weeks. <strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer,it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?</strong> A)2 B)4 C)8 D)12 E)None of the above
According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer,it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?

A)2
B)4
C)8
D)12
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
63
Table 11-3 <strong>Table 11-3   According to Table 11-3,there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer,what mean and variance would be used?</strong> A)20 and 4.222 B)30 and 5.222 C)20 and 5.222 D)30 and 4.222 E)22.667 and 1.111
According to Table 11-3,there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer,what mean and variance would be used?

A)20 and 4.222
B)30 and 5.222
C)20 and 5.222
D)30 and 4.222
E)22.667 and 1.111
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
64
The critical path of a network is the

A)path with the least variance.
B)path with zero slack.
C)path with the most activities.
D)path with the largest variance.
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
65
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?

A)108.0
B)110.4
C)89.6
D)85.0
E)100
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
66
Table 11-3 <strong>Table 11-3   According to Table 11-3,there are five activities in a PERT project.What is the variance of the critical path?</strong> A)5.222 B)4.222 C)1.222 D)0 E)1.111
According to Table 11-3,there are five activities in a PERT project.What is the variance of the critical path?

A)5.222
B)4.222
C)1.222
D)0
E)1.111
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
67
Table 11-2
The following represents a project with four activities.All times are in weeks. <strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals. )</strong> A)0.07 B)0.93 C)0.43 D)0.77 E)None of the above
According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals. )

A)0.07
B)0.93
C)0.43
D)0.77
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
68
CPM stands for

A)critical path management.
B)critical project management.
C)critical project method.
D)critical path method.
E)centralized project management.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
69
The two common techniques for drawing PERT networks are

A)NOA and NRA.
B)AON and AOA.
C)GANTT and NOA.
D)ONA and OAO.
E)CAN and CAA.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
70
In a PERT network,the latest (activity)start time is the

A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
71
In PERT,we assume that

A)the times to complete individual activities are known with certainty.
B)all activities are carried out by staff from our own organization.
C)the total cost of a project is independent of the time to complete the project.
D)the total time to complete all activities on the critical path is described by a normal distribution.
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
72
Table 11-2
The following represents a project with four activities.All times are in weeks. <strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to the data in Table 11-2,what is the minimum expected completion time for the project?</strong> A)18 B)19 C)37 D)11 E)None of the above
According to the data in Table 11-2,what is the minimum expected completion time for the project?

A)18
B)19
C)37
D)11
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
73
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 13 days respectively,compute the expected time for this activity.

A)3
B)4
C)5
D)6
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
74
PERT stands for

A)probabilistic evaluation and review technique.
B)program evaluation and review technique.
C)probability of expected run times.
D)program of expected run times.
E)project evaluation and review technique.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
75
Which of the following questions can be answered by PERT?

A)When will the entire project be completed?
B)What is the probability that the project will be completed by a specific date?
C)What are the critical activities?
D)What are the noncritical activities?
E)All of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
76
The work breakdown structure involves identifying the ________ for each activity.

A)time
B)cost
C)resource requirements
D)predecessors
E)All of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
77
Table 11-3 <strong>Table 11-3   According to Table 11-3,there are five activities in a PERT project.Which activities are on the critical path?</strong> A)A-B-C-D-E B)A-C-E C)B-D D)A-B-C-D E)B-E
According to Table 11-3,there are five activities in a PERT project.Which activities are on the critical path?

A)A-B-C-D-E
B)A-C-E
C)B-D
D)A-B-C-D
E)B-E
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
78
In PERT analysis,the probability of the optimistic time occurring should be on the order of

A)1/2.
B)1/3.
C)1/6.
D)1/10.
E)1/100.
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
79
The expected time in PERT is

A)greater than the most likely time.
B)equal to the most likely time.
C)less than the most likely time.
D)Any of the above
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
80
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,7,and 11 days respectively,compute the expected time for this activity.

A)5
B)6
C)7
D)12
E)None of the above
Unlock Deck
Unlock for access to all 134 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 134 flashcards in this deck.