Deck 10: Project Scheduling: Lagging, Crashing, and Activity Networks

Full screen (f)
exit full mode
Question
The critical path may not contain a dummy activity.
Use Space or
up arrow
down arrow
to flip the card.
Question
An activity of duration zero whose sole purpose is to maintain network logic is a(n) __________.
Question
The horizontal axis for a Gantt chart is __________.
Question
The logical relationship between the start and finish of one activity and the start and finish of another activity is the __________.
Question
Most project management software employs AOA diagramming
Question
The three principal methods for accelerating project activities are to change the __________, __________, and __________ of the project resources.
Question
__________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.
Question
Quite often the marginal gains in employee productivity decrease dramatically with the increased use of overtime.
Question
Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.
Question
PERT analysis is based on __________ estimates, which, if unreasonably determined, can lead to inaccurate and misleading project schedules.
Question
In order to accelerate completion of a project, the manager must crash critical path activities.
Question
The process of accelerating a project is referred to as __________.
Question
In analyzing crash options for project activities, each activity has a slope that is calculated as the __________ divided by the __________.
Question
Networks are adaptable and useful for all scheduling challenges that an organization faces.
Question
The least common type of lag relationship occurs when a successor's finish is dependent upon a predecessor's start.
Question
Finish to start lags are the same as additional activity slack.
Question
Gantt charts cannot depict float.
Question
The primary drawback with __________ networks occurs when the project is very complex, with numerous paths through the model.
Question
If a project is extraordinarily complex, rather than showing every possible path through the network and every activity sequence, a(n) __________ that shows only the key subroutines or network paths can be created.
Question
AOA is a more useful technique than AON if the project is complex and has many significant milestones.
Question
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 3 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 3 <div style=padding-top: 35px>

A) Resource 4
B) Resource 2
C) Resource 1
D) Resource 3
Question
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5 <div style=padding-top: 35px>

A) Resource 1
B) Resource 2
C) Resource 4
D) Resource 5
Question
Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4 day lag between activities C and B? <strong>Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4 day lag between activities C and B?  </strong> A) The early finish for A increases to 31. B) The early start time for A increases to 24. C) The early finish time for B increases to 31. D) The early start time for D falls to 23. <div style=padding-top: 35px>

A) The early finish for A increases to 31.
B) The early start time for A increases to 24.
C) The early finish time for B increases to 31.
D) The early start time for D falls to 23.
Question
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis. How much slack is available in The Great Hair Washing project? <strong>Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis. How much slack is available in The Great Hair Washing project?  </strong> A) 10 minutes B) 15 minutes C) 0 minutes D) 5 minutes <div style=padding-top: 35px>

A) 10 minutes
B) 15 minutes
C) 0 minutes
D) 5 minutes
Question
A finish to start lag delay is usually shown:

A) as an added value in the predecessor's activity time.
B) on the line adjoining the two activity nodes.
C) as an added value in the predecessors early start time.
D) as a subtracted value in the follower's early finish time.
Question
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A) Resource 4 B) Resource 2 C) Resource 3 D) Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A) Resource 4 B) Resource 2 C) Resource 3 D) Resource 5 <div style=padding-top: 35px>

A) Resource 4
B) Resource 2
C) Resource 3
D) Resource 5
Question
The most common type of logical sequencing between tasks is referred to as the:

A) finish to start relationship.
B) finish to finish relationship.
C) start to start relationship.
D) start to finish relationship.
Question
Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown. Which statement is best? <strong>Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown. Which statement is best?  </strong> A) a < d B) a < c C) b < c D) d < a <div style=padding-top: 35px>

A) a < d
B) a < c
C) b < c
D) d < a
Question
Use the Gantt chart and the activity list to determine which resource is used the least. <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A) Resource 1 B) Resource 3 C) Resource 4 D) Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A) Resource 1 B) Resource 3 C) Resource 4 D) Resource 2 <div style=padding-top: 35px>

A) Resource 1
B) Resource 3
C) Resource 4
D) Resource 2
Question
Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2 <div style=padding-top: 35px>

A) Resource 4
B) Resource 3
C) Resource 1
D) Resource 2
Question
Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A) Resource 2 B) Resource 3 C) Resource 1 D) Resource 4 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A) Resource 2 B) Resource 3 C) Resource 1 D) Resource 4 <div style=padding-top: 35px>

A) Resource 2
B) Resource 3
C) Resource 1
D) Resource 4
Question
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A) Resource 3 B) Resource 1 C) Resource 2 D) Resource 4 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A) Resource 3 B) Resource 1 C) Resource 2 D) Resource 4 <div style=padding-top: 35px>

A) Resource 3
B) Resource 1
C) Resource 2
D) Resource 4
Question
Which statement about this Gantt chart is best? <strong>Which statement about this Gantt chart is best?  </strong> A) Activity a has a duration that could be as short as 1 day and as long as 10. B) Activity b probably has activity a as a predecessor. C) No progress has been made on activity c. D) Activity d is the longest activity. <div style=padding-top: 35px>

A) Activity a has a duration that could be as short as 1 day and as long as 10.
B) Activity b probably has activity a as a predecessor.
C) No progress has been made on activity c.
D) Activity d is the longest activity.
Question
What is the early start time for activity C if it has the start to start relationship shown? <strong>What is the early start time for activity C if it has the start to start relationship shown?  </strong> A) day 20 B) day 25 C) day 27 D) day 29 <div style=padding-top: 35px>

A) day 20
B) day 25
C) day 27
D) day 29
Question
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 5 <div style=padding-top: 35px>

A) Resource 4
B) Resource 2
C) Resource 1
D) Resource 5
Question
Use the Gantt chart and the activity list to determine when resource 5 is free. <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60 <div style=padding-top: 35px>

A) between 0 and 15
B) between 15 and 30
C) between 30 and 45
D) between 45 and 60
Question
Use the Gantt chart and activity list to determine when resource 3 is free. <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A) between 0 and 10 B) between 10 and 20 C) between 20 and 30 D) between 30 and 40 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A) between 0 and 10 B) between 10 and 20 C) between 20 and 30 D) between 30 and 40 <div style=padding-top: 35px>

A) between 0 and 10
B) between 10 and 20
C) between 20 and 30
D) between 30 and 40
Question
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5 <div style=padding-top: 35px>

A) Resource 1
B) Resource 2
C) Resource 4
D) Resource 5
Question
Use the Gantt chart and the activity list to determine which resource is used the most. <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2 <div style=padding-top: 35px>

A) Resource 4
B) Resource 3
C) Resource 1
D) Resource 2
Question
Use the Gantt chart and the activity list to determine when resource 2 is free. <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60 <div style=padding-top: 35px>

A) between 0 and 15
B) between 15 and 30
C) between 30 and 45
D) between 45 and 60
Question
If an activity's cost is plotted against its duration on axes with zeros at the origin:

A) the slope of the line is positive because it costs more to finish an activity more quickly.
B) the slope of the line is negative because a shorter activity costs less than a longer one.
C) the slope of the line is negative because it costs more to finish an activity more quickly.
D) the slope of the line is positive because a longer activity costs more than a shorter one.
Question
Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A) Resource 2 B) Resource 4 C) Resource 1 D) Resource 3 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A) Resource 2 B) Resource 4 C) Resource 1 D) Resource 3 <div style=padding-top: 35px>

A) Resource 2
B) Resource 4
C) Resource 1
D) Resource 3
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks. What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks. What is the lowest total cost for completing this project?  </strong> A) $222,667 B) $217,000 C) $222,000 D) $208,000 <div style=padding-top: 35px>

A) $222,667
B) $217,000
C) $222,000
D) $208,000
Question
A basic Gantt chart:

A) clearly displays early and late start and finish times for all activities.
B) cannot be used to track the project's progress.
C) permits scheduling resources well before they are needed.
D) shows dummy activities to preserve network logic.
Question
Use the information in the table (all times are in days) to determine the lowest extra cost for a 20-day project. <strong>Use the information in the table (all times are in days) to determine the lowest extra cost for a 20-day project.  </strong> A) $200 B) $130 C) $120 D) $100 <div style=padding-top: 35px>

A) $200
B) $130
C) $120
D) $100
Question
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000. Due to slippage on the critical path you need to reduce this activity by three weeks. If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000, what is the slope for the activity?

A) $20,000 per week
B) $33,333 per week
C) $5,000 per week
D) $13,333 per week
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days?  </strong> A) $253,000 B) $237,000 C) $216,000 D) $207,000 <div style=padding-top: 35px>

A) $253,000
B) $237,000
C) $216,000
D) $207,000
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 40 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 40 days?  </strong> A) $242,667 B) $255,600 C) $263,333 D) $272,500 <div style=padding-top: 35px>

A) $242,667
B) $255,600
C) $263,333
D) $272,500
Question
Given the cost information in the table, what is the cheapest activity to crash on a per week basis? <strong>Given the cost information in the table, what is the cheapest activity to crash on a per week basis?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D <div style=padding-top: 35px>

A) Activity A
B) Activity B
C) Activity C
D) Activity D
Question
Use the information in the table (all times are in days) to determine the lowest cost minimum completion time? <strong>Use the information in the table (all times are in days) to determine the lowest cost minimum completion time?  </strong> A) $1,040 B) $1,020 C) $740 D) $720 <div style=padding-top: 35px>

A) $1,040
B) $1,020
C) $740
D) $720
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks. What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks. What is the lowest total cost for completing this project?  </strong> A) $234,000 B) $255,600 C) $248,333 D) $252,000 <div style=padding-top: 35px>

A) $234,000
B) $255,600
C) $248,333
D) $252,000
Question
Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project. <strong>Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project.  </strong> A) $380 B) $400 C) $420 D) $440 <div style=padding-top: 35px>

A) $380
B) $400
C) $420
D) $440
Question
An activity on an arrow network:

A) cannot have more arrows than nodes.
B) cannot have more nodes than arrows.
C) has one more node than arrows.
D) has one more arrow than nodes.
Question
The most common method for shortening activity durations involves the decision to:

A) eliminate bureaucracy.
B) alter the technology used in the activity.
C) assign more senior personnel to the activity.
D) increase project resources.
Question
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 45 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 45 days?  </strong> A) $222,667 B) $243,675 C) $258,333 D) $272,500 <div style=padding-top: 35px>

A) $222,667
B) $243,675
C) $258,333
D) $272,500
Question
One reason for crashing a project is:

A) the project has slipped behind schedule.
B) that the initial schedule may be too pessimistic.
C) market needs change and the project is not in demand any more.
D) there are no repercussions for delivering the project late.
Question
The process of accelerating a project is referred to as:

A) streamlining.
B) expediting.
C) rushing.
D) crashing.
Question
Which of these approaches will NOT accelerate the completion of a project?

A) Improve the productivity of existing project resources.
B) Increase the bureaucratic oversight.
C) Improve the working method.
D) Increase the quantity of personnel and equipment.
Question
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week. In order to complete this activity within 10 weeks, you must hire additional general laborers at a cost of $2,000 per week. What is the slope for this activity?

A) $0 per week
B) $1,000 per week
C) $2,000 per week
D) $6,000 per week
Question
It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity. Use this information to determine the lowest cost for this project. All times given are in days. <strong>It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity. Use this information to determine the lowest cost for this project. All times given are in days.  </strong> A) $1,800 B) $1,770 C) $1,700 D) $1,630 <div style=padding-top: 35px>

A) $1,800
B) $1,770
C) $1,700
D) $1,630
Question
Networks would not be well suited for:

A) planning a construction project.
B) planning a wedding.
C) planning a software upgrade.
D) planning monthly production.
Question
Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days.
Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days.  <div style=padding-top: 35px>
Question
A complex project that is managed using a top-down, bottom-up approach to network diagrams means that:

A) management's top-down portion of the network contains the greatest detail.
B) top management does not have a basis for understanding the actual development of the project.
C) the top tier summary network does not give top management the basis for understanding the actual development of the project.
D) the bottom level information cannot be understood by those performing the actual work.
Question
What is project crashing and what are three reasons why it might be important to do so?
Question
An AOA network:

A) cannot show a merge activity.
B) cannot show a burst activity.
C) cannot have consecutive merge and burst activities.
D) can have all of the features described in A-C above.
Question
Sketch a network and use it as an example as you discuss the four different logical relationships between activities.
Question
What are the three principal methods for accelerating a project and under what circumstances might these methods yield little gain?
Question
AON networks have an advantage over AOA networks:

A) if the project under study is complex.
B) because they don't need dummy activities.
C) in the construction industry because they are the norm.
D) when it is critical to highlight milestones.
Question
The fastest completion time for this project is: <strong>The fastest completion time for this project is:  </strong> A) 14 B) 15 C) 16 D) 17 <div style=padding-top: 35px>

A) 14
B) 15
C) 16
D) 17
Question
When involved in a project involving many subcontractors:

A) it is imperative that the network is a mutually accessible document.
B) one subcontractor's network diagram should never be shown to another for ethical reasons.
C) PERT/CPM should not be used.
D) it is illegal to reveal one subcontractor's plan to another.
Question
What is a Gantt chart, what information does one provide, and what are the benefits of using one?
Question
The best approach to network representation of a large and hugely complex project is to:

A) represent all activities and relationships.
B) simplify network logic and reduce it to the most meaningful relationships.
C) use AOA.
D) use AON.
Question
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A) zero dummy activities B) one dummy activity. C) two dummy activities. D) three dummy activities. <div style=padding-top: 35px>

A) zero dummy activities
B) one dummy activity.
C) two dummy activities.
D) three dummy activities.
Question
Dummy activities have a duration equal to the:

A) slack on the critical path.
B) length of the predecessor.
C) length of the successor.
D) lag needed to preserve network logic.
Question
Research has shown that, in general,:

A) there is a tendency to underestimate activity lengths.
B) there is a tendency to overestimate activity lengths.
C) the activity lengths are estimated correctly.
D) the activity lengths are estimated correctly but the networks are drawn incorrectly.
Question
What information is NOT included in the nodes for an AOA network?

A) label
B) early start time
C) late finish time
D) early finish time
Question
The critical path of this network is: <strong>The critical path of this network is:  </strong> A) 14 B) 15 C) 12 D) 13 <div style=padding-top: 35px>

A) 14
B) 15
C) 12
D) 13
Question
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A) zero dummy activities B) one dummy activity. C) two dummy activities. D) three dummy activities. <div style=padding-top: 35px>

A) zero dummy activities
B) one dummy activity.
C) two dummy activities.
D) three dummy activities.
Question
AOA networks have an advantage over AON networks:

A) if the project is complex.
B) because they are easier to read for novices.
C) when it comes to software packages for project management.
D) when the task of network labeling is considered.
Question
A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be? A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?      <div style=padding-top: 35px> A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?      <div style=padding-top: 35px> A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?      <div style=padding-top: 35px>
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/90
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 10: Project Scheduling: Lagging, Crashing, and Activity Networks
1
The critical path may not contain a dummy activity.
False
2
An activity of duration zero whose sole purpose is to maintain network logic is a(n) __________.
dummy activity
3
The horizontal axis for a Gantt chart is __________.
time
4
The logical relationship between the start and finish of one activity and the start and finish of another activity is the __________.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
5
Most project management software employs AOA diagramming
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
6
The three principal methods for accelerating project activities are to change the __________, __________, and __________ of the project resources.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
7
__________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
8
Quite often the marginal gains in employee productivity decrease dramatically with the increased use of overtime.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
9
Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
10
PERT analysis is based on __________ estimates, which, if unreasonably determined, can lead to inaccurate and misleading project schedules.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
11
In order to accelerate completion of a project, the manager must crash critical path activities.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
12
The process of accelerating a project is referred to as __________.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
13
In analyzing crash options for project activities, each activity has a slope that is calculated as the __________ divided by the __________.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
14
Networks are adaptable and useful for all scheduling challenges that an organization faces.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
15
The least common type of lag relationship occurs when a successor's finish is dependent upon a predecessor's start.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
16
Finish to start lags are the same as additional activity slack.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
17
Gantt charts cannot depict float.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
18
The primary drawback with __________ networks occurs when the project is very complex, with numerous paths through the model.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
19
If a project is extraordinarily complex, rather than showing every possible path through the network and every activity sequence, a(n) __________ that shows only the key subroutines or network paths can be created.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
20
AOA is a more useful technique than AON if the project is complex and has many significant milestones.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
21
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 3 <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 3

A) Resource 4
B) Resource 2
C) Resource 1
D) Resource 3
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
22
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5

A) Resource 1
B) Resource 2
C) Resource 4
D) Resource 5
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
23
Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4 day lag between activities C and B? <strong>Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4 day lag between activities C and B?  </strong> A) The early finish for A increases to 31. B) The early start time for A increases to 24. C) The early finish time for B increases to 31. D) The early start time for D falls to 23.

A) The early finish for A increases to 31.
B) The early start time for A increases to 24.
C) The early finish time for B increases to 31.
D) The early start time for D falls to 23.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
24
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis. How much slack is available in The Great Hair Washing project? <strong>Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis. How much slack is available in The Great Hair Washing project?  </strong> A) 10 minutes B) 15 minutes C) 0 minutes D) 5 minutes

A) 10 minutes
B) 15 minutes
C) 0 minutes
D) 5 minutes
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
25
A finish to start lag delay is usually shown:

A) as an added value in the predecessor's activity time.
B) on the line adjoining the two activity nodes.
C) as an added value in the predecessors early start time.
D) as a subtracted value in the follower's early finish time.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
26
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A) Resource 4 B) Resource 2 C) Resource 3 D) Resource 5 <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A) Resource 4 B) Resource 2 C) Resource 3 D) Resource 5

A) Resource 4
B) Resource 2
C) Resource 3
D) Resource 5
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
27
The most common type of logical sequencing between tasks is referred to as the:

A) finish to start relationship.
B) finish to finish relationship.
C) start to start relationship.
D) start to finish relationship.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
28
Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown. Which statement is best? <strong>Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown. Which statement is best?  </strong> A) a < d B) a < c C) b < c D) d < a

A) a < d
B) a < c
C) b < c
D) d < a
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
29
Use the Gantt chart and the activity list to determine which resource is used the least. <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A) Resource 1 B) Resource 3 C) Resource 4 D) Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A) Resource 1 B) Resource 3 C) Resource 4 D) Resource 2

A) Resource 1
B) Resource 3
C) Resource 4
D) Resource 2
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
30
Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2

A) Resource 4
B) Resource 3
C) Resource 1
D) Resource 2
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
31
Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A) Resource 2 B) Resource 3 C) Resource 1 D) Resource 4 <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A) Resource 2 B) Resource 3 C) Resource 1 D) Resource 4

A) Resource 2
B) Resource 3
C) Resource 1
D) Resource 4
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
32
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A) Resource 3 B) Resource 1 C) Resource 2 D) Resource 4 <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A) Resource 3 B) Resource 1 C) Resource 2 D) Resource 4

A) Resource 3
B) Resource 1
C) Resource 2
D) Resource 4
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
33
Which statement about this Gantt chart is best? <strong>Which statement about this Gantt chart is best?  </strong> A) Activity a has a duration that could be as short as 1 day and as long as 10. B) Activity b probably has activity a as a predecessor. C) No progress has been made on activity c. D) Activity d is the longest activity.

A) Activity a has a duration that could be as short as 1 day and as long as 10.
B) Activity b probably has activity a as a predecessor.
C) No progress has been made on activity c.
D) Activity d is the longest activity.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
34
What is the early start time for activity C if it has the start to start relationship shown? <strong>What is the early start time for activity C if it has the start to start relationship shown?  </strong> A) day 20 B) day 25 C) day 27 D) day 29

A) day 20
B) day 25
C) day 27
D) day 29
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
35
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 5

A) Resource 4
B) Resource 2
C) Resource 1
D) Resource 5
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
36
Use the Gantt chart and the activity list to determine when resource 5 is free. <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60 <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60

A) between 0 and 15
B) between 15 and 30
C) between 30 and 45
D) between 45 and 60
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
37
Use the Gantt chart and activity list to determine when resource 3 is free. <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A) between 0 and 10 B) between 10 and 20 C) between 20 and 30 D) between 30 and 40 <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A) between 0 and 10 B) between 10 and 20 C) between 20 and 30 D) between 30 and 40

A) between 0 and 10
B) between 10 and 20
C) between 20 and 30
D) between 30 and 40
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
38
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5

A) Resource 1
B) Resource 2
C) Resource 4
D) Resource 5
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
39
Use the Gantt chart and the activity list to determine which resource is used the most. <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2

A) Resource 4
B) Resource 3
C) Resource 1
D) Resource 2
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
40
Use the Gantt chart and the activity list to determine when resource 2 is free. <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60 <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A) between 0 and 15 B) between 15 and 30 C) between 30 and 45 D) between 45 and 60

A) between 0 and 15
B) between 15 and 30
C) between 30 and 45
D) between 45 and 60
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
41
If an activity's cost is plotted against its duration on axes with zeros at the origin:

A) the slope of the line is positive because it costs more to finish an activity more quickly.
B) the slope of the line is negative because a shorter activity costs less than a longer one.
C) the slope of the line is negative because it costs more to finish an activity more quickly.
D) the slope of the line is positive because a longer activity costs more than a shorter one.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
42
Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A) Resource 2 B) Resource 4 C) Resource 1 D) Resource 3 <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A) Resource 2 B) Resource 4 C) Resource 1 D) Resource 3

A) Resource 2
B) Resource 4
C) Resource 1
D) Resource 3
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
43
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks. What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks. What is the lowest total cost for completing this project?  </strong> A) $222,667 B) $217,000 C) $222,000 D) $208,000

A) $222,667
B) $217,000
C) $222,000
D) $208,000
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
44
A basic Gantt chart:

A) clearly displays early and late start and finish times for all activities.
B) cannot be used to track the project's progress.
C) permits scheduling resources well before they are needed.
D) shows dummy activities to preserve network logic.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
45
Use the information in the table (all times are in days) to determine the lowest extra cost for a 20-day project. <strong>Use the information in the table (all times are in days) to determine the lowest extra cost for a 20-day project.  </strong> A) $200 B) $130 C) $120 D) $100

A) $200
B) $130
C) $120
D) $100
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
46
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000. Due to slippage on the critical path you need to reduce this activity by three weeks. If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000, what is the slope for the activity?

A) $20,000 per week
B) $33,333 per week
C) $5,000 per week
D) $13,333 per week
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
47
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days?  </strong> A) $253,000 B) $237,000 C) $216,000 D) $207,000

A) $253,000
B) $237,000
C) $216,000
D) $207,000
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
48
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 40 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 40 days?  </strong> A) $242,667 B) $255,600 C) $263,333 D) $272,500

A) $242,667
B) $255,600
C) $263,333
D) $272,500
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
49
Given the cost information in the table, what is the cheapest activity to crash on a per week basis? <strong>Given the cost information in the table, what is the cheapest activity to crash on a per week basis?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D

A) Activity A
B) Activity B
C) Activity C
D) Activity D
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
50
Use the information in the table (all times are in days) to determine the lowest cost minimum completion time? <strong>Use the information in the table (all times are in days) to determine the lowest cost minimum completion time?  </strong> A) $1,040 B) $1,020 C) $740 D) $720

A) $1,040
B) $1,020
C) $740
D) $720
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
51
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks. What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks. What is the lowest total cost for completing this project?  </strong> A) $234,000 B) $255,600 C) $248,333 D) $252,000

A) $234,000
B) $255,600
C) $248,333
D) $252,000
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
52
Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project. <strong>Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project.  </strong> A) $380 B) $400 C) $420 D) $440

A) $380
B) $400
C) $420
D) $440
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
53
An activity on an arrow network:

A) cannot have more arrows than nodes.
B) cannot have more nodes than arrows.
C) has one more node than arrows.
D) has one more arrow than nodes.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
54
The most common method for shortening activity durations involves the decision to:

A) eliminate bureaucracy.
B) alter the technology used in the activity.
C) assign more senior personnel to the activity.
D) increase project resources.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
55
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 45 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 45 days?  </strong> A) $222,667 B) $243,675 C) $258,333 D) $272,500

A) $222,667
B) $243,675
C) $258,333
D) $272,500
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
56
One reason for crashing a project is:

A) the project has slipped behind schedule.
B) that the initial schedule may be too pessimistic.
C) market needs change and the project is not in demand any more.
D) there are no repercussions for delivering the project late.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
57
The process of accelerating a project is referred to as:

A) streamlining.
B) expediting.
C) rushing.
D) crashing.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
58
Which of these approaches will NOT accelerate the completion of a project?

A) Improve the productivity of existing project resources.
B) Increase the bureaucratic oversight.
C) Improve the working method.
D) Increase the quantity of personnel and equipment.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
59
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week. In order to complete this activity within 10 weeks, you must hire additional general laborers at a cost of $2,000 per week. What is the slope for this activity?

A) $0 per week
B) $1,000 per week
C) $2,000 per week
D) $6,000 per week
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
60
It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity. Use this information to determine the lowest cost for this project. All times given are in days. <strong>It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity. Use this information to determine the lowest cost for this project. All times given are in days.  </strong> A) $1,800 B) $1,770 C) $1,700 D) $1,630

A) $1,800
B) $1,770
C) $1,700
D) $1,630
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
61
Networks would not be well suited for:

A) planning a construction project.
B) planning a wedding.
C) planning a software upgrade.
D) planning monthly production.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
62
Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days.
Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
63
A complex project that is managed using a top-down, bottom-up approach to network diagrams means that:

A) management's top-down portion of the network contains the greatest detail.
B) top management does not have a basis for understanding the actual development of the project.
C) the top tier summary network does not give top management the basis for understanding the actual development of the project.
D) the bottom level information cannot be understood by those performing the actual work.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
64
What is project crashing and what are three reasons why it might be important to do so?
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
65
An AOA network:

A) cannot show a merge activity.
B) cannot show a burst activity.
C) cannot have consecutive merge and burst activities.
D) can have all of the features described in A-C above.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
66
Sketch a network and use it as an example as you discuss the four different logical relationships between activities.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
67
What are the three principal methods for accelerating a project and under what circumstances might these methods yield little gain?
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
68
AON networks have an advantage over AOA networks:

A) if the project under study is complex.
B) because they don't need dummy activities.
C) in the construction industry because they are the norm.
D) when it is critical to highlight milestones.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
69
The fastest completion time for this project is: <strong>The fastest completion time for this project is:  </strong> A) 14 B) 15 C) 16 D) 17

A) 14
B) 15
C) 16
D) 17
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
70
When involved in a project involving many subcontractors:

A) it is imperative that the network is a mutually accessible document.
B) one subcontractor's network diagram should never be shown to another for ethical reasons.
C) PERT/CPM should not be used.
D) it is illegal to reveal one subcontractor's plan to another.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
71
What is a Gantt chart, what information does one provide, and what are the benefits of using one?
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
72
The best approach to network representation of a large and hugely complex project is to:

A) represent all activities and relationships.
B) simplify network logic and reduce it to the most meaningful relationships.
C) use AOA.
D) use AON.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
73
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A) zero dummy activities B) one dummy activity. C) two dummy activities. D) three dummy activities.

A) zero dummy activities
B) one dummy activity.
C) two dummy activities.
D) three dummy activities.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
74
Dummy activities have a duration equal to the:

A) slack on the critical path.
B) length of the predecessor.
C) length of the successor.
D) lag needed to preserve network logic.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
75
Research has shown that, in general,:

A) there is a tendency to underestimate activity lengths.
B) there is a tendency to overestimate activity lengths.
C) the activity lengths are estimated correctly.
D) the activity lengths are estimated correctly but the networks are drawn incorrectly.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
76
What information is NOT included in the nodes for an AOA network?

A) label
B) early start time
C) late finish time
D) early finish time
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
77
The critical path of this network is: <strong>The critical path of this network is:  </strong> A) 14 B) 15 C) 12 D) 13

A) 14
B) 15
C) 12
D) 13
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
78
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A) zero dummy activities B) one dummy activity. C) two dummy activities. D) three dummy activities.

A) zero dummy activities
B) one dummy activity.
C) two dummy activities.
D) three dummy activities.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
79
AOA networks have an advantage over AON networks:

A) if the project is complex.
B) because they are easier to read for novices.
C) when it comes to software packages for project management.
D) when the task of network labeling is considered.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
80
A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be? A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?      A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?      A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 90 flashcards in this deck.