Deck 3: Managing Systems Projects

Full screen (f)
exit full mode
Question
A project manager should never develop time and cost estimates based on the resources used for previously developed information systems.
Use Space or
up arrow
down arrow
to flip the card.
Question
In a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)chart,each rectangular box,called a task box,has five sections that contain important information about a task.
Question
Critical time is the amount of time that the task could be late without pushing back the completion date of the entire project.
Question
Using a work breakdown structure (WBS)allows one to manage a project as one large task.
Question
Quantitative risk analysis evaluates each risk by estimating the probability that it will occur and the degree of impact.
Question
If team members lack experience with certain aspects of the required technology,temporary help might be obtained from IT consultants or part-time staff.
Question
The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars,time,project scope,or quality.
Question
Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)and Gantt charts are mutually exclusive techniques.
Question
The prior experience method to make time and cost estimates works best for large projects.
Question
The three legs of the project triangle are management,staff,and clients.
Question
Generally,systems analysts review the work of other systems analysts,and programmers review the work of other programmers,as a form of peer review,in structured walk-throughs.
Question
In most systems analysis tasks,time and people are interchangeable.
Question
System developers can initiate a formal project as early as the preliminary investigation stage,or later on,as analysis,design,and implementation activities occur.
Question
Weight is an importance value that is added to each duration estimate.
Question
When tasks must be completed one after another,they are called concurrent tasks.
Question
In addition to tasks,every project has events,or milestones.
Question
Scheduling involves selecting and staffing the project team and assigning specific tasks to team members.
Question
If any task along a critical path falls behind schedule,the entire project will be delayed.
Question
Henry L.Gantt developed Gantt charts almost 100 years ago.
Question
The task name should be unique in the project.
Question
Progress reports may be given verbally to immediate supervisors,management,and users.
Question
A _____ involves breaking a project down into a series of smaller tasks.

A) work breakdown structure (WBS)
B) value breakdown structure (VBS)
C) risk breakdown structure (RBS)
D) concept breakdown structure (CBS)
Question
The three legs of a project triangle are _____,scope,and time.

A) requirements
B) resources
C) environment
D) cost
Question
Frederick Brooks,Jr.observed that adding manpower to a late software project makes completion faster.
Question
The task duration is the same as the elapsed time.
Question
If the project manager fails to plan,staff,organize,supervise,communicate,motivate,evaluate,direct,and control properly,then the project is certain to fail.
Question
The first step in the creation of a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)chart is to _____.

A) select the graphical planning aids to use
B) determine the logical order of project tasks
C) determine the status of all tasks
D) identify all the project tasks
Question
Project planning,an activity of a project manager,_____.

A) requires guiding,supervising,and coordinating the a project team's workload
B) includes monitoring the progress of the a project,evaluating results,and taking corrective action when necessary to stay on target
C) focuses on long-term challenges and goals,the importance of stakeholders,and a commitment to the firm's role as a corporate citizen
D) includes identifying project tasks and estimating completion times and costs
Question
Project reporting,an activity of a project manager,_____.

A) involves the creation of a specific timetable,usually in the form of charts that show tasks,task dependencies,and critical tasks that might delay a project
B) includes informing management,users,and the project team about the progress of a project
C) consists of staffing,which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
Question
Project scheduling,an activity of a project manager,_____.

A) requires guiding,supervising,and coordinating a project team's workload
B) includes monitoring the progress of a project,evaluating results,and taking corrective action when necessary to stay on target
C) involves staffing,which includes selecting the project team and assigning specific tasks to team members
D) includes budgeting a project based on the number of modules and their complexity in a project
Question
Project monitoring,an activity of a project manager,_____.

A) requires guiding,supervising,and coordinating a project team's workload
B) involves the creation of a specific timetable,usually in the form of charts that show tasks,task dependencies,and critical tasks that might delay a project
C) consists of staffing,which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
Question
Using a(n)_____,a project manager can convert task start and finish times to actual dates by laying out the entire project on a calendar.

A) XY chart
B) Pedigree chart
C) Program Evaluation Review Technique (PERT)chart
D) Scatter chart
Question
Qualitative risk analysis can involve a modeling process called what-if analysis,which allows a project manager to vary one or more element(s)in a model to measure the effect on other elements.
Question
A project _____ negotiates with users who might have conflicting requirements or want changes that would require additional time or expense.

A) manager
B) reporter
C) tester
D) coordinator
Question
Tasks are basic units of work that the project manager plans,schedules,and monitors.
Question
Effective project reporting requires _____.

A) strong communication skills
B) strong intervention skills
C) strong negotiation skills
D) strong leadership skills
Question
A project schedule will not be accurate if the underlying task pattern is incorrect.
Question
A risk response plan is a proactive effort to anticipate a risk and describe an action plan to deal with it.
Question
GanttProject is a free open-source Java-based project management tool that is available on multiple platforms.
Question
Gantt charts are more useful for scheduling,monitoring,and controlling the actual work than PERT charts.
Question
When maintaining schedules,if enough _____ and frequent checkpoints exist,problems will be detected rapidly.

A) activity diagrams
B) milestones
C) data flow diagrams
D) viewports
Question
Two or more _____ depend on a predecessor task.

A) dependent tasks
B) concurrent tasks
C) ancestor tasks
D) precursor tasks
Question
A _____ might involve maximums for one or more resources,such as time,dollars,or people.

A) successor task
B) constraint
C) task ID
D) milestone
Question
Often,two or more concurrent tasks depend on a single prior task,which is called a _____.

A) predecessor task
B) wireframe task
C) beneficiary task
D) discrete task
Question
A(n)_____ is a recognizable reference point that can be used to monitor progress.

A) event
B) notification
C) alert
D) task
Question
A _____ is a sequence of tasks that has no slack time.

A) risk path
B) foundation path
C) baseline path
D) critical path
Question
_____ give the project managers an opportunity to seek input and conduct brainstorming sessions.

A) Status reports
B) Project review reports
C) Project status meetings
D) Board meetings
Question
When several tasks can start at the same time,each is called a(n)_____ task.

A) model
B) asynchronous
C) baseline
D) concurrent
Question
A _____ chart displays complex task patterns and relationships.

A) Gantt
B) Pareto
C) Program Evaluation Review Technique (PERT)
D) Scatter
Question
_____ give team members of a project an opportunity to share information,discuss common problems,and explain new techniques.

A) Board meetings
B) Project status meetings
C) Project review reports
D) Status reports
Question
Project managers always must be aware of the _____,so they can monitor the vital tasks and keep a project on track.

A) absolute path
B) relative path
C) critical path
D) dynamic path
Question
A _____ cannot be started until a previous task is completed.

A) dependent task
B) predecessor task
C) precursor task
D) concurrent task
Question
The first step in creating a work breakdown structure (WBS)is to _____.

A) mark all recognizable events
B) determine time requirements
C) list all tasks
D) estimate task completion time and cost
Question
A(n)_____ is a series of tasks that,if delayed,would affect the completion date of the overall project.

A) critical path
B) dynamic path
C) absolute path
D) relative path
Question
The _____ is the most pessimistic outcome of a task.

A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) dominant-case estimate (D)
Question
_____ is a full-featured program that holds the dominant share of the project management software market.

A) Apptivo
B) GanttProject
C) Microsoft Project
D) Gantter
Question
A _____ is a review of a project team member's work by other members of a team.

A) critical walk-through
B) foundational walk-through
C) baseline walk-through
D) structured walk-through
Question
When two or more concurrent tasks depend on a single prior task,each of the concurrent tasks is called a(n)_____.

A) successor task
B) discrete task
C) antecedent task
D) descendent task
Question
A(n)_____ is a condition,restriction,or requirement that the system must satisfy.

A) constraint
B) index
C) milestone
D) viewport
Question
A _____ represents the work that one person can complete in one day.

A) person-day
B) work-day
C) work-duration
D) person-work
Question
Briefly explain the tasks performed by a project manager.
Question
_____,a human resource issue,is a possible cause of cost overruns in an organization.

A) Inadequate training
B) Inaccurate demand forecast
C) Poor monitoring of progress
D) Unrealistic estimates
Question
When a project manager first recognizes that a project is in trouble,one of the options available to the manager is _____.

A) delaying the project deadline
B) expanding the project requirements
C) reducing the project resources
D) eliminating controls and procedures
Question
Explain the difference between qualitative and quantitative risk analysis.
Question
Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days,but most likely will require 20 days.What is the 20 day estimate called?

A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) logistical estimate (L)
Question
_____ can involve a modeling process called what-if analysis,which allows a project manager to vary one or more element(s)in a model to measure the effect on other elements.

A) Qualitative risk analysis
B) Quantitative risk analysis
C) Resource list analysis
D) Trigger analysis
Question
_____,a free cloud-based project management tool,runs in a browser window,so there is no software to install to use it.

A) Apptivo
B) Smartsheet
C) Microsoft Project
D) Gantter
Question
Explain the three legs of a project triangle.What makes it challenging?
Question
A _____ is a proactive effort to anticipate a risk and describe an action plan to deal with it.

A) risk identification plan
B) risk response plan
C) risk balance plan
D) risk management plan
Question
A _____ consists of horizontal bars,connected with arrows that indicate task dependencies.

A) Gantt chart
B) viewport
C) Scatter chart
D) wireframe
Question
_____ lists each risk and assesses the likelihood that it could affect a project.

A) Risk averting
B) Risk dominance
C) Risk identification
D) Risk analytics
Question
A continuous risk-tracking process can _____.

A) notice changes in existing risks
B) revert reported risks
C) prevent human resource turnover issues
D) prevent new issues
Question
A _____ includes a review of a project's scope,stakeholders,budget,schedule,and any other internal or external factors that might affect the project.

A) change management plan
B) configuration management plan
C) debt management plan
D) risk management plan
Question
Mauricio has decided to use a project management tool for this project.He wants the tool to be free and cloud-based so that there is no need for software to be installed.Help Mauricio in identifying the project management tool that best fits the purpose.

A) SPSS
B) Scoro
C) Microsoft Project
D) Gantter
Question
Briefly explain how project progress is reported and evaluated.
Question
Define risk and give a basic list of risk management steps.
Question
A _____ displays the same information as the Gantt chart,including task dependencies,but uses task boxes to include much more detail.

A) semantic wireframe
B) mesh topology
C) ring topology
D) network diagram
Question
A(n)_____ is an event that could affect a project negatively.

A) issue
B) webinar
C) uncertainty
D) risk
Question
A Gantt chart can simplify a complex project by combining several activities into a task _____ that contains subsidiary tasks.

A) group
B) hierarchy
C) network
D) bar
Question
Adding more people to a project actually might increase the time necessary to complete the project because of a principle called _____.

A) Brooks' law
B) Bernoulli's law
C) Hooke's law
D) Moody's law
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/80
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 3: Managing Systems Projects
1
A project manager should never develop time and cost estimates based on the resources used for previously developed information systems.
False
2
In a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)chart,each rectangular box,called a task box,has five sections that contain important information about a task.
True
3
Critical time is the amount of time that the task could be late without pushing back the completion date of the entire project.
False
4
Using a work breakdown structure (WBS)allows one to manage a project as one large task.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
5
Quantitative risk analysis evaluates each risk by estimating the probability that it will occur and the degree of impact.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
6
If team members lack experience with certain aspects of the required technology,temporary help might be obtained from IT consultants or part-time staff.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
7
The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars,time,project scope,or quality.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
8
Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)and Gantt charts are mutually exclusive techniques.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
9
The prior experience method to make time and cost estimates works best for large projects.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
10
The three legs of the project triangle are management,staff,and clients.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
11
Generally,systems analysts review the work of other systems analysts,and programmers review the work of other programmers,as a form of peer review,in structured walk-throughs.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
12
In most systems analysis tasks,time and people are interchangeable.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
13
System developers can initiate a formal project as early as the preliminary investigation stage,or later on,as analysis,design,and implementation activities occur.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
14
Weight is an importance value that is added to each duration estimate.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
15
When tasks must be completed one after another,they are called concurrent tasks.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
16
In addition to tasks,every project has events,or milestones.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
17
Scheduling involves selecting and staffing the project team and assigning specific tasks to team members.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
18
If any task along a critical path falls behind schedule,the entire project will be delayed.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
19
Henry L.Gantt developed Gantt charts almost 100 years ago.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
20
The task name should be unique in the project.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
21
Progress reports may be given verbally to immediate supervisors,management,and users.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
22
A _____ involves breaking a project down into a series of smaller tasks.

A) work breakdown structure (WBS)
B) value breakdown structure (VBS)
C) risk breakdown structure (RBS)
D) concept breakdown structure (CBS)
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
23
The three legs of a project triangle are _____,scope,and time.

A) requirements
B) resources
C) environment
D) cost
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
24
Frederick Brooks,Jr.observed that adding manpower to a late software project makes completion faster.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
25
The task duration is the same as the elapsed time.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
26
If the project manager fails to plan,staff,organize,supervise,communicate,motivate,evaluate,direct,and control properly,then the project is certain to fail.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
27
The first step in the creation of a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)chart is to _____.

A) select the graphical planning aids to use
B) determine the logical order of project tasks
C) determine the status of all tasks
D) identify all the project tasks
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
28
Project planning,an activity of a project manager,_____.

A) requires guiding,supervising,and coordinating the a project team's workload
B) includes monitoring the progress of the a project,evaluating results,and taking corrective action when necessary to stay on target
C) focuses on long-term challenges and goals,the importance of stakeholders,and a commitment to the firm's role as a corporate citizen
D) includes identifying project tasks and estimating completion times and costs
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
29
Project reporting,an activity of a project manager,_____.

A) involves the creation of a specific timetable,usually in the form of charts that show tasks,task dependencies,and critical tasks that might delay a project
B) includes informing management,users,and the project team about the progress of a project
C) consists of staffing,which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
30
Project scheduling,an activity of a project manager,_____.

A) requires guiding,supervising,and coordinating a project team's workload
B) includes monitoring the progress of a project,evaluating results,and taking corrective action when necessary to stay on target
C) involves staffing,which includes selecting the project team and assigning specific tasks to team members
D) includes budgeting a project based on the number of modules and their complexity in a project
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
31
Project monitoring,an activity of a project manager,_____.

A) requires guiding,supervising,and coordinating a project team's workload
B) involves the creation of a specific timetable,usually in the form of charts that show tasks,task dependencies,and critical tasks that might delay a project
C) consists of staffing,which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
32
Using a(n)_____,a project manager can convert task start and finish times to actual dates by laying out the entire project on a calendar.

A) XY chart
B) Pedigree chart
C) Program Evaluation Review Technique (PERT)chart
D) Scatter chart
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
33
Qualitative risk analysis can involve a modeling process called what-if analysis,which allows a project manager to vary one or more element(s)in a model to measure the effect on other elements.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
34
A project _____ negotiates with users who might have conflicting requirements or want changes that would require additional time or expense.

A) manager
B) reporter
C) tester
D) coordinator
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
35
Tasks are basic units of work that the project manager plans,schedules,and monitors.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
36
Effective project reporting requires _____.

A) strong communication skills
B) strong intervention skills
C) strong negotiation skills
D) strong leadership skills
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
37
A project schedule will not be accurate if the underlying task pattern is incorrect.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
38
A risk response plan is a proactive effort to anticipate a risk and describe an action plan to deal with it.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
39
GanttProject is a free open-source Java-based project management tool that is available on multiple platforms.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
40
Gantt charts are more useful for scheduling,monitoring,and controlling the actual work than PERT charts.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
41
When maintaining schedules,if enough _____ and frequent checkpoints exist,problems will be detected rapidly.

A) activity diagrams
B) milestones
C) data flow diagrams
D) viewports
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
42
Two or more _____ depend on a predecessor task.

A) dependent tasks
B) concurrent tasks
C) ancestor tasks
D) precursor tasks
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
43
A _____ might involve maximums for one or more resources,such as time,dollars,or people.

A) successor task
B) constraint
C) task ID
D) milestone
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
44
Often,two or more concurrent tasks depend on a single prior task,which is called a _____.

A) predecessor task
B) wireframe task
C) beneficiary task
D) discrete task
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
45
A(n)_____ is a recognizable reference point that can be used to monitor progress.

A) event
B) notification
C) alert
D) task
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
46
A _____ is a sequence of tasks that has no slack time.

A) risk path
B) foundation path
C) baseline path
D) critical path
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
47
_____ give the project managers an opportunity to seek input and conduct brainstorming sessions.

A) Status reports
B) Project review reports
C) Project status meetings
D) Board meetings
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
48
When several tasks can start at the same time,each is called a(n)_____ task.

A) model
B) asynchronous
C) baseline
D) concurrent
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
49
A _____ chart displays complex task patterns and relationships.

A) Gantt
B) Pareto
C) Program Evaluation Review Technique (PERT)
D) Scatter
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
50
_____ give team members of a project an opportunity to share information,discuss common problems,and explain new techniques.

A) Board meetings
B) Project status meetings
C) Project review reports
D) Status reports
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
51
Project managers always must be aware of the _____,so they can monitor the vital tasks and keep a project on track.

A) absolute path
B) relative path
C) critical path
D) dynamic path
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
52
A _____ cannot be started until a previous task is completed.

A) dependent task
B) predecessor task
C) precursor task
D) concurrent task
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
53
The first step in creating a work breakdown structure (WBS)is to _____.

A) mark all recognizable events
B) determine time requirements
C) list all tasks
D) estimate task completion time and cost
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
54
A(n)_____ is a series of tasks that,if delayed,would affect the completion date of the overall project.

A) critical path
B) dynamic path
C) absolute path
D) relative path
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
55
The _____ is the most pessimistic outcome of a task.

A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) dominant-case estimate (D)
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
56
_____ is a full-featured program that holds the dominant share of the project management software market.

A) Apptivo
B) GanttProject
C) Microsoft Project
D) Gantter
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
57
A _____ is a review of a project team member's work by other members of a team.

A) critical walk-through
B) foundational walk-through
C) baseline walk-through
D) structured walk-through
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
58
When two or more concurrent tasks depend on a single prior task,each of the concurrent tasks is called a(n)_____.

A) successor task
B) discrete task
C) antecedent task
D) descendent task
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
59
A(n)_____ is a condition,restriction,or requirement that the system must satisfy.

A) constraint
B) index
C) milestone
D) viewport
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
60
A _____ represents the work that one person can complete in one day.

A) person-day
B) work-day
C) work-duration
D) person-work
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
61
Briefly explain the tasks performed by a project manager.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
62
_____,a human resource issue,is a possible cause of cost overruns in an organization.

A) Inadequate training
B) Inaccurate demand forecast
C) Poor monitoring of progress
D) Unrealistic estimates
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
63
When a project manager first recognizes that a project is in trouble,one of the options available to the manager is _____.

A) delaying the project deadline
B) expanding the project requirements
C) reducing the project resources
D) eliminating controls and procedures
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
64
Explain the difference between qualitative and quantitative risk analysis.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
65
Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days,but most likely will require 20 days.What is the 20 day estimate called?

A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) logistical estimate (L)
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
66
_____ can involve a modeling process called what-if analysis,which allows a project manager to vary one or more element(s)in a model to measure the effect on other elements.

A) Qualitative risk analysis
B) Quantitative risk analysis
C) Resource list analysis
D) Trigger analysis
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
67
_____,a free cloud-based project management tool,runs in a browser window,so there is no software to install to use it.

A) Apptivo
B) Smartsheet
C) Microsoft Project
D) Gantter
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
68
Explain the three legs of a project triangle.What makes it challenging?
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
69
A _____ is a proactive effort to anticipate a risk and describe an action plan to deal with it.

A) risk identification plan
B) risk response plan
C) risk balance plan
D) risk management plan
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
70
A _____ consists of horizontal bars,connected with arrows that indicate task dependencies.

A) Gantt chart
B) viewport
C) Scatter chart
D) wireframe
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
71
_____ lists each risk and assesses the likelihood that it could affect a project.

A) Risk averting
B) Risk dominance
C) Risk identification
D) Risk analytics
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
72
A continuous risk-tracking process can _____.

A) notice changes in existing risks
B) revert reported risks
C) prevent human resource turnover issues
D) prevent new issues
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
73
A _____ includes a review of a project's scope,stakeholders,budget,schedule,and any other internal or external factors that might affect the project.

A) change management plan
B) configuration management plan
C) debt management plan
D) risk management plan
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
74
Mauricio has decided to use a project management tool for this project.He wants the tool to be free and cloud-based so that there is no need for software to be installed.Help Mauricio in identifying the project management tool that best fits the purpose.

A) SPSS
B) Scoro
C) Microsoft Project
D) Gantter
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
75
Briefly explain how project progress is reported and evaluated.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
76
Define risk and give a basic list of risk management steps.
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
77
A _____ displays the same information as the Gantt chart,including task dependencies,but uses task boxes to include much more detail.

A) semantic wireframe
B) mesh topology
C) ring topology
D) network diagram
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
78
A(n)_____ is an event that could affect a project negatively.

A) issue
B) webinar
C) uncertainty
D) risk
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
79
A Gantt chart can simplify a complex project by combining several activities into a task _____ that contains subsidiary tasks.

A) group
B) hierarchy
C) network
D) bar
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
80
Adding more people to a project actually might increase the time necessary to complete the project because of a principle called _____.

A) Brooks' law
B) Bernoulli's law
C) Hooke's law
D) Moody's law
Unlock Deck
Unlock for access to all 80 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 80 flashcards in this deck.