Deck 5: Capacity Management

Full screen (f)
exit full mode
Question
What variables affect capacity available in a production environment?
Use Space or
up arrow
down arrow
to flip the card.
Question
Over a 4- week period, a work center produced 540 standard hours of work, was available for work 640 hours, and actually worked 480 hours. Calculate the utilization and the efficiency fo the work center.
Question
What is back scheduling and what must be known for each order to schedule?
Question
What are the steps in calculating work center load?
Question
Product__________ depend on the design of the product and the mix of products made.

A) specification and mix
B) specification
C) work effort
D) mix
Question
A work center consisting of 7 machines is operated 16 hours a day for a 5- day week. Utilization is 80% and efficiency is 110%. What is the rated weekly capacity in standard hours?
Question
The__________ time is the time a job waits at a work center before being handled.

A) wait
B) lead
C) queue
D) move
Question
A work center produces 120 units in a shift. THe standard for that item is 100 units a shift. What is the efficiency of the work center?

A) 1.2%
B) 100%
C) 120%
D) 80%
Question
In 1 week, a work center produces 85 standard hours of work. The hours scheduled are 80. But 75 hours are actually worked. Calculate the utilization and efficiency of the work center.
Question
__________is responsible for determining the capacity needed to achieve the priority plans as well as providing, monitoring, and controlling that capacity so the priority plan can be met.

A) Capacity planning
B) Capacity required
C) Capacity management
D) Capacity control
Question
Capacity is a__________ of doing work, not the__________ of work done.

A) rate, standard
B) rate, quantity
C) standard, rate
D) quantity, rate
Question
A work center is to process 150 units of gear shaft SG 123 on work order 333. The setup time is 1.5 hours and the run time is 0.2 hours per piece. What is the standard time needed to run the order?
Question
What information should exist for every component in the routing file?
Question
A work center file contains information on:

A) capacity
B) wait and queue time
C) move times
D) all of the above
Question
Over the previous 4 weeks, a work center produced 120, 130, 150, and 140 standard hours of work. What is the demonstrated capacity of the work center in standard hours?

A) 125
B) 135
C) 155
D) 145
Question
__________is the process of determining the resources required to meet the priority plan and the methods needed to make that capacity available.

A) Capacity management
B) Capacity control
C) Capacity planning
D) Capacity required
Question
__________is the capacity of a system or resource needed to product a desired output in a given time period.

A) Capacity management
B) Capacity required
C) Capacity planning
D) Capacity control
Question
Demonstrated capacity is figured from:

A) utilization
B) historical data
C) efficiency
D) available time
Question
A work center consists of 4 machines, each working a 16- hour day for 5 days a week. What is the weekly time available?
Question
What are the inputs needed for a CRP and how can it be obtained?
Question
The time needed for each order is the sum of the setup time and the queue time.
Question
Capacity available is the capacity of a system or resource to produce a quantity of output in a given time period.
Question
It is possible for a work center to utilize 100 hours a week but not produce 100 standard hours of work.
Question
A work center is composed of a number of machines or workers capable of doing a variety of different jobs.
Question
Most orders are processed in only one work center.
Question
Capacity requirements planning occurs at the material requirements planning level.
Question
Rated or calculated capacity is the number of hours a work center can be used.
Question
An open shop order appears as a scheduled receipt on the material requirements plan.
Question
Determining the capacity required begins with determining the time needed for each order at each work center then summing up the capacity required for individual orders to obtain the load.
Question
The result of capacity requirements planning should be a detailed workable plan that meets the priority objectives and provides the capacity to do so.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/30
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 5: Capacity Management
1
What variables affect capacity available in a production environment?
Capacity available is affected by product specifications, product mix, plant and equipment and work effort. Product specifications and product mix depend on the design of the product and the mix of products made.
2
Over a 4- week period, a work center produced 540 standard hours of work, was available for work 640 hours, and actually worked 480 hours. Calculate the utilization and the efficiency fo the work center.
Utilization - 480/640 * 100% = 75% Efficiency = 540/480 * 100% = 112.5%
3
What is back scheduling and what must be known for each order to schedule?
Back scheduling is a process that starts with the due date and using the lead times, works backward to find the start date for each operation. To schedule the following must be known: quantity and due date, sequence of operations and work centers needed, setup and run times for each operation, queue, wait, and move times, and the work center capacity available rated or demonstrated).
4
What are the steps in calculating work center load?
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
5
Product__________ depend on the design of the product and the mix of products made.

A) specification and mix
B) specification
C) work effort
D) mix
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
6
A work center consisting of 7 machines is operated 16 hours a day for a 5- day week. Utilization is 80% and efficiency is 110%. What is the rated weekly capacity in standard hours?
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
7
The__________ time is the time a job waits at a work center before being handled.

A) wait
B) lead
C) queue
D) move
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
8
A work center produces 120 units in a shift. THe standard for that item is 100 units a shift. What is the efficiency of the work center?

A) 1.2%
B) 100%
C) 120%
D) 80%
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
9
In 1 week, a work center produces 85 standard hours of work. The hours scheduled are 80. But 75 hours are actually worked. Calculate the utilization and efficiency of the work center.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
10
__________is responsible for determining the capacity needed to achieve the priority plans as well as providing, monitoring, and controlling that capacity so the priority plan can be met.

A) Capacity planning
B) Capacity required
C) Capacity management
D) Capacity control
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
11
Capacity is a__________ of doing work, not the__________ of work done.

A) rate, standard
B) rate, quantity
C) standard, rate
D) quantity, rate
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
12
A work center is to process 150 units of gear shaft SG 123 on work order 333. The setup time is 1.5 hours and the run time is 0.2 hours per piece. What is the standard time needed to run the order?
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
13
What information should exist for every component in the routing file?
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
14
A work center file contains information on:

A) capacity
B) wait and queue time
C) move times
D) all of the above
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
15
Over the previous 4 weeks, a work center produced 120, 130, 150, and 140 standard hours of work. What is the demonstrated capacity of the work center in standard hours?

A) 125
B) 135
C) 155
D) 145
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
16
__________is the process of determining the resources required to meet the priority plan and the methods needed to make that capacity available.

A) Capacity management
B) Capacity control
C) Capacity planning
D) Capacity required
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
17
__________is the capacity of a system or resource needed to product a desired output in a given time period.

A) Capacity management
B) Capacity required
C) Capacity planning
D) Capacity control
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
18
Demonstrated capacity is figured from:

A) utilization
B) historical data
C) efficiency
D) available time
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
19
A work center consists of 4 machines, each working a 16- hour day for 5 days a week. What is the weekly time available?
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
20
What are the inputs needed for a CRP and how can it be obtained?
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
21
The time needed for each order is the sum of the setup time and the queue time.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
22
Capacity available is the capacity of a system or resource to produce a quantity of output in a given time period.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
23
It is possible for a work center to utilize 100 hours a week but not produce 100 standard hours of work.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
24
A work center is composed of a number of machines or workers capable of doing a variety of different jobs.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
25
Most orders are processed in only one work center.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
26
Capacity requirements planning occurs at the material requirements planning level.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
27
Rated or calculated capacity is the number of hours a work center can be used.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
28
An open shop order appears as a scheduled receipt on the material requirements plan.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
29
Determining the capacity required begins with determining the time needed for each order at each work center then summing up the capacity required for individual orders to obtain the load.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
30
The result of capacity requirements planning should be a detailed workable plan that meets the priority objectives and provides the capacity to do so.
Unlock Deck
Unlock for access to all 30 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 30 flashcards in this deck.