Deck 6: Interpreting the Contract

Full screen (f)
exit full mode
Question
After the contract is agreed upon, the Contract Administrator should still get issues and interpretations in writing
Use Space or
up arrow
down arrow
to flip the card.
Question
Substantial completion is when the Owner can use the structure for its intended purpose
Question
Warranties begin upon installation of the equipment
Question
Contracts are almost always written by the party in control
Question
It is better to find solutions among friends than to find faults
Question
Sworn testimony about what is not written but intended by the Contract will usually negate the wording of the contract
Question
Which of these could be part of the contract

A) General Conditions
B) Bid Proposal
C) Addenda
D) All of these
Question
Contracts are usually written

A) to get more than the Owner paid for
B) to protect everyone at the same time
C) by the party in control
D) after the full scope of work is known
Question
Could be part of the contract

A) General Conditions
B) Bid Proposal
C) Addenda
D) All of these
Question
There are two types of ambiguities-patent and

A) latent
B) non-patent
C) immediate
D) errors and omissions
Question
Two clauses that help interpret the contract as a whole are the

A) scope and Precedence clauses
B) scope and risk shifting clauses
C) scope and exculpatory clauses
D) scope and insurance clauses
Question
The first level of interpreting a Contract will rely upon

A) what was intended by both parties
B) what testimony can reveal about one or the other party's intentions
C) what is reasonable and logical to an outside observer
D) what the owner wanted as being more important than what the Contractor thought
Question
When submitting an RFI, the Contractor should if possible

A) provide proof that the design is deficient
B) submit pricing
C) submit a preferred solution
D) ask for an immediate meeting to resolve the issue so the schedule will not be affected
Question
Although many may have a say, a Contractor can rely upon a structure being substantially complete for Contract purposes when

A) the Owner says it is
B) the Owner can use it for its intended purposes
C) the Architect says it is
D) the City Inspector says it is
Question
Cardinal changes

A) can be based on scope or quantity
B) are important and should be done immediately
C) are normally small (like the bird) but can seriously change the schedule
D) are generally only involved in Federal work
Question
Liquidated damages result from

A) water damage usually during the foundation stage
B) water damage during any part of the construction
C) failing to meet the completion date
D) the owner becoming bankrupt and going out of business
Question
Means and methods will

A) always be provided to the Constructor
B) will seldom be provided to the Constructor
C) is no longer an issue on IPD projects
D) cannot replace new technology in the construction process
Question
The Spearin Doctrine

A) relieves the Contractor from design flaws in documents provided by the Owner
B) puts all parties on notice for their own risks
C) eliminates the need for arbitration or mediation
D) is used by Design Professionals to place burden of performance on the Contractor
Question
The Spearin Doctrine relieves Design Professionals from responsibility for errors in the design
Question
A Subcontractor cannot be held responsible for a low price proposal based on bad judgment
Question
Generally specific will govern over general in a Contract
Question
Once submitted by the Constructor, the Design Professional will be held responsible for delays related to answering the RFI
Question
Warranties always start when the equipment is installed
Question
Parol evidence carries more weight than most other types of evidence
Question
Ambiguities can either be patent or inconsequential
Question
Doubling the scope of the Contract could be considered a Cardinal change
Question
The Architect is always allowed to make changes that do not cost the Owner money, but not changes that would add or deduct from the Contract price
Question
A ""crash"" is when the work of two or more trades ""collide"" on 3-dimensional drawings
Question
Estoppel is a bar preventing a party to act in a manner contrary to the way it has acted in the past
Question
A ""flow down"" clause places responsibility of Contract requirements on a lower-tier entity
Question
Float can only be used by the Contractor
Question
Joint ventures are formed by the Owner to get better pricing or cost savings
Question
Liquidated damages refer to damages that are removed from the Contract by the Owner
Question
Design Professionals are required by the Owner to give the Constructor the best ""means and methods"" for accomplishing the construction
Question
Mediation is a binding process for resolving disputes
Question
Parol evidence is given by a party to avoid further litigation
Question
A precedence clause can sometimes help resolve an ambiguity
Question
Based on ___, one party cannot withdraw its obligations if it knows the other party relied upon its actions or offer.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/38
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 6: Interpreting the Contract
1
After the contract is agreed upon, the Contract Administrator should still get issues and interpretations in writing
True
2
Substantial completion is when the Owner can use the structure for its intended purpose
True
3
Warranties begin upon installation of the equipment
False
4
Contracts are almost always written by the party in control
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
5
It is better to find solutions among friends than to find faults
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
6
Sworn testimony about what is not written but intended by the Contract will usually negate the wording of the contract
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
7
Which of these could be part of the contract

A) General Conditions
B) Bid Proposal
C) Addenda
D) All of these
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
8
Contracts are usually written

A) to get more than the Owner paid for
B) to protect everyone at the same time
C) by the party in control
D) after the full scope of work is known
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
9
Could be part of the contract

A) General Conditions
B) Bid Proposal
C) Addenda
D) All of these
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
10
There are two types of ambiguities-patent and

A) latent
B) non-patent
C) immediate
D) errors and omissions
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
11
Two clauses that help interpret the contract as a whole are the

A) scope and Precedence clauses
B) scope and risk shifting clauses
C) scope and exculpatory clauses
D) scope and insurance clauses
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
12
The first level of interpreting a Contract will rely upon

A) what was intended by both parties
B) what testimony can reveal about one or the other party's intentions
C) what is reasonable and logical to an outside observer
D) what the owner wanted as being more important than what the Contractor thought
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
13
When submitting an RFI, the Contractor should if possible

A) provide proof that the design is deficient
B) submit pricing
C) submit a preferred solution
D) ask for an immediate meeting to resolve the issue so the schedule will not be affected
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
14
Although many may have a say, a Contractor can rely upon a structure being substantially complete for Contract purposes when

A) the Owner says it is
B) the Owner can use it for its intended purposes
C) the Architect says it is
D) the City Inspector says it is
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
15
Cardinal changes

A) can be based on scope or quantity
B) are important and should be done immediately
C) are normally small (like the bird) but can seriously change the schedule
D) are generally only involved in Federal work
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
16
Liquidated damages result from

A) water damage usually during the foundation stage
B) water damage during any part of the construction
C) failing to meet the completion date
D) the owner becoming bankrupt and going out of business
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
17
Means and methods will

A) always be provided to the Constructor
B) will seldom be provided to the Constructor
C) is no longer an issue on IPD projects
D) cannot replace new technology in the construction process
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
18
The Spearin Doctrine

A) relieves the Contractor from design flaws in documents provided by the Owner
B) puts all parties on notice for their own risks
C) eliminates the need for arbitration or mediation
D) is used by Design Professionals to place burden of performance on the Contractor
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
19
The Spearin Doctrine relieves Design Professionals from responsibility for errors in the design
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
20
A Subcontractor cannot be held responsible for a low price proposal based on bad judgment
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
21
Generally specific will govern over general in a Contract
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
22
Once submitted by the Constructor, the Design Professional will be held responsible for delays related to answering the RFI
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
23
Warranties always start when the equipment is installed
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
24
Parol evidence carries more weight than most other types of evidence
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
25
Ambiguities can either be patent or inconsequential
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
26
Doubling the scope of the Contract could be considered a Cardinal change
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
27
The Architect is always allowed to make changes that do not cost the Owner money, but not changes that would add or deduct from the Contract price
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
28
A ""crash"" is when the work of two or more trades ""collide"" on 3-dimensional drawings
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
29
Estoppel is a bar preventing a party to act in a manner contrary to the way it has acted in the past
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
30
A ""flow down"" clause places responsibility of Contract requirements on a lower-tier entity
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
31
Float can only be used by the Contractor
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
32
Joint ventures are formed by the Owner to get better pricing or cost savings
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
33
Liquidated damages refer to damages that are removed from the Contract by the Owner
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
34
Design Professionals are required by the Owner to give the Constructor the best ""means and methods"" for accomplishing the construction
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
35
Mediation is a binding process for resolving disputes
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
36
Parol evidence is given by a party to avoid further litigation
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
37
A precedence clause can sometimes help resolve an ambiguity
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
38
Based on ___, one party cannot withdraw its obligations if it knows the other party relied upon its actions or offer.
Unlock Deck
Unlock for access to all 38 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 38 flashcards in this deck.