Deck 11: Getting Started
1
Fortunately, Constructive Acceleration guarantees the Contractor will be compensated for additional costs related to extra work required to meet the original schedule
False
2
In most cases, the Contract Administrator has to recognize that finding fault is not finding a solution
True
3
Without a change order clause in the Contract
A) the Owner can do whatever he/she wants
B) the Owner cannot require a change be performed by the Contractor
C) no one gets paid for changes made to the Contract
D) the contract is invalid
A) the Owner can do whatever he/she wants
B) the Owner cannot require a change be performed by the Contractor
C) no one gets paid for changes made to the Contract
D) the contract is invalid
B
4
In most cases, a flaw or ambiguity in the Contract documents
A) will be construed against the drafter of the documents
B) will be paid for the person in the weakest negotiating position
C) can cause a severe strain on the schedule
D) is minor and does not require immediate notice
A) will be construed against the drafter of the documents
B) will be paid for the person in the weakest negotiating position
C) can cause a severe strain on the schedule
D) is minor and does not require immediate notice
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
5
Until one knows otherwise
A) the Contract Administrator should consider any change a chance to improve profit
B) the Contract Administrator should consider any change a potential to affect the schedule
C) a change requires immediate resolution before it hinders group rapport
D) a change should be discussed at the next progress meeting
A) the Contract Administrator should consider any change a chance to improve profit
B) the Contract Administrator should consider any change a potential to affect the schedule
C) a change requires immediate resolution before it hinders group rapport
D) a change should be discussed at the next progress meeting
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
6
If a change affects the schedule
A) the Owner and Architect will know
B) the Contract Administrator should document and notify the Architect and Owner
C) pricing of the change should be submitted immediately
D) a solution must first be found before notifying all concerned
A) the Owner and Architect will know
B) the Contract Administrator should document and notify the Architect and Owner
C) pricing of the change should be submitted immediately
D) a solution must first be found before notifying all concerned
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
7
Constructive changes
A) have a positive effect on the morale of the workforce
B) always make the Constructor a reasonable profit
C) may seem insignificant when first asked for by the Owner, but they can require additional cost and time as they are performed
D) do not require notice since they would be documented by the actual work constructed
A) have a positive effect on the morale of the workforce
B) always make the Constructor a reasonable profit
C) may seem insignificant when first asked for by the Owner, but they can require additional cost and time as they are performed
D) do not require notice since they would be documented by the actual work constructed
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
8
Characteristic of a Critical Path Schedule is
A) there can be float on all but the critical path itself
B) only the critical portion of the project is what is shown so everyone can concentrate on that section
C) it eliminates the need for Constructive Acceleration
D) it eliminates the need for directed acceleration
A) there can be float on all but the critical path itself
B) only the critical portion of the project is what is shown so everyone can concentrate on that section
C) it eliminates the need for Constructive Acceleration
D) it eliminates the need for directed acceleration
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
9
The Eichleay formula was developed for
A) private work and later adopted by public work
B) Federal work
C) field costs that are never fully compensated
D) additional payroll burdens that are paid by the contractor but not part of the employees take home pay
A) private work and later adopted by public work
B) Federal work
C) field costs that are never fully compensated
D) additional payroll burdens that are paid by the contractor but not part of the employees take home pay
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
10
Sometimes the requirements of proof and detail are so burdensome that a small change does not pay for itself
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
11
The Owner can grant to an agent the authority to make changes
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
12
Constructive changes can seemingly be clarification of the intended work, but they can lead to additional costs
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
13
Ambiguities will always be ""construed against the drafter"" of the documents containing the ambiguity
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
14
Float on the critical path gives everyone a chance to catch up with the project schedule
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
15
Directed Acceleration will be compensated for once the costs are determined
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
16
The Eichleay formula is used to determine field overhead
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
17
Fast tracking is one method to shorten a schedule
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
18
The Measured Mile approach utilizes costs per unit put in place incurred during a specific time in the project when production should be appropriate for that unit
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
19
A Patent Ambiguity is one that no one could have anticipated
Unlock Deck
Unlock for access to all 20 flashcards in this deck.
Unlock Deck
k this deck
20
The ""Measured Mile""
A) is useful in highway but not vertical construction
B) is only used in Federal work
C) requires accurate measurement to be considered reasonable
D) is a concept that cannot be used in the metric system of measurement
A) is useful in highway but not vertical construction
B) is only used in Federal work
C) requires accurate measurement to be considered reasonable
D) is a concept that cannot be used in the metric system of measurement