Deck 15: Project Management Online
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/82
Play
Full screen (f)
Deck 15: Project Management Online
1
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

Two techniques that were developed to help managers plan, organize, and control projects are: the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT).
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


Two techniques that were developed to help managers plan, organize, and control projects are: the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT).
True
2
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

The main difference between CPM and PERT is that
A) CPM is deterministic and PERT is probabilistic
B) CPM is probabilisttic and PERT is deterministic
C) CPM is best for longer projects while PERT is best for shorter projects
D) CPM requires 3 duration estimates for each activity while PERT requires only one duration estimate for each activity
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


The main difference between CPM and PERT is that
A) CPM is deterministic and PERT is probabilistic
B) CPM is probabilisttic and PERT is deterministic
C) CPM is best for longer projects while PERT is best for shorter projects
D) CPM requires 3 duration estimates for each activity while PERT requires only one duration estimate for each activity
CPM is deterministic and PERT is probabilistic
3
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day?
A) =(C3-E3)/(F3-D3)
B) =(F3-D3)/(C3-E3)
C) =(F3)/(C3-E3)
D) =(F3-D3)/(E3)
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day?

A) =(C3-E3)/(F3-D3)
B) =(F3-D3)/(C3-E3)
C) =(F3)/(C3-E3)
D) =(F3-D3)/(E3)
=(F3-D3)/(C3-E3)
4
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

In a project network there must be a unique critical path.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


In a project network there must be a unique critical path.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
5
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

Which of the following is true regarding projects?
A) Projects can have a unique start activity and a unique finish activity.
B) Projects can have multiple start activities and a unique finish activity.
C) Projects can have multiple start and finish activities.
D) All of these are true regarding projects.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


Which of the following is true regarding projects?
A) Projects can have a unique start activity and a unique finish activity.
B) Projects can have multiple start activities and a unique finish activity.
C) Projects can have multiple start and finish activities.
D) All of these are true regarding projects.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
6
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

In Project Management the early start (ES) and early finish (EF) times for each activity are determined by using a backward pass.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


In Project Management the early start (ES) and early finish (EF) times for each activity are determined by using a backward pass.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
7
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

In CPM, the duration of the project
A) is equal to the duration of the critical path
B) is determined by managers
C) is determined by investors
D) is determined by a supervising government agency
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


In CPM, the duration of the project
A) is equal to the duration of the critical path
B) is determined by managers
C) is determined by investors
D) is determined by a supervising government agency
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
8
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

If the following project must be completed by day 18 at minimum cost how do we change the LP model?
A) Enter 18 in cell E14.
B) Add a constraint that E14 ≤ 18.
C) Make cell E14 the target cell.
D) Add a constraint that E14 = 18.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


If the following project must be completed by day 18 at minimum cost how do we change the LP model?

A) Enter 18 in cell E14.
B) Add a constraint that E14 ≤ 18.
C) Make cell E14 the target cell.
D) Add a constraint that E14 = 18.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
9
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Analytic Solver Platform (ASP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?
A) =IF(E3≤(C3-E3)/(D3-B3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)),B3+SQRT((D3-E3)*(C3-B3)*E3))
B) =IF(E3≤(D3-B3)/(C3-E3),B3+SQRT((D3-E3)*(C3-B3)*E3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)))
C) =IF(E3≤(C3-E3)/(D3-B3),B3-SQRT((D3-E3)*(C3-B3)*E3),D3+SQRT((D3-B3)*(D3-C3)*(1-E3)))
D) =PsiTriangular(B3,C3,D3)
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Analytic Solver Platform (ASP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?

A) =IF(E3≤(C3-E3)/(D3-B3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)),B3+SQRT((D3-E3)*(C3-B3)*E3))
B) =IF(E3≤(D3-B3)/(C3-E3),B3+SQRT((D3-E3)*(C3-B3)*E3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)))
C) =IF(E3≤(C3-E3)/(D3-B3),B3-SQRT((D3-E3)*(C3-B3)*E3),D3+SQRT((D3-B3)*(D3-C3)*(1-E3)))
D) =PsiTriangular(B3,C3,D3)
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
10
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

A way to crash an activity is to
A) spend extra money
B) subcontract
C) use overtime
D) all of the above
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


A way to crash an activity is to
A) spend extra money
B) subcontract
C) use overtime
D) all of the above
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
11
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

Slack is the amount of time by which the start of an activity can be delayed without delaying the project.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


Slack is the amount of time by which the start of an activity can be delayed without delaying the project.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
12
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

What is the correct formula to compute the expected duration of an activity using PERT?
A)
B)
C)
D)
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


What is the correct formula to compute the expected duration of an activity using PERT?
A)

B)

C)

D)

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
13
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

The purpose of the forward pass in the Critical Path Method (CPM) technique is to
A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


The purpose of the forward pass in the Critical Path Method (CPM) technique is to
A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
14
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

Noncritical activities have some negative amount of slack.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


Noncritical activities have some negative amount of slack.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
15
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

Array formulas typically perform operations on one or more ranges of cells.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


Array formulas typically perform operations on one or more ranges of cells.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
16
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

Which activities have slack in the following diagram?
A) A, C, D, F
B) B, E
C) A, C, D, E
D) B, D, E
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


Which activities have slack in the following diagram?

A) A, C, D, F
B) B, E
C) A, C, D, E
D) B, D, E
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
17
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

A Gantt chart is a popular technique for portraying the schedule of a project's activities over time.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


A Gantt chart is a popular technique for portraying the schedule of a project's activities over time.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
18
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

Two network design techniques used in Project Management are: the Activity-On-Node (AON) and the Activity on Arcs (AOA).
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


Two network design techniques used in Project Management are: the Activity-On-Node (AON) and the Activity on Arcs (AOA).
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
19
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

In deciding which activities to crash, select
A) activities on the critical path(s)
B) all activities with positive slack time
C) longest activities
D) lowest cost activities
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


In deciding which activities to crash, select
A) activities on the critical path(s)
B) all activities with positive slack time
C) longest activities
D) lowest cost activities
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
20
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

If we are employing Activity-On-Node (AON) network design, the arcs in the network diagram represent
A) significance relationships.
B) precedence relationships.
C) tasks to complete.
D) task times.
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


If we are employing Activity-On-Node (AON) network design, the arcs in the network diagram represent
A) significance relationships.
B) precedence relationships.
C) tasks to complete.
D) task times.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
21
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

A weakness of Gantt charts is that they do not explicitly
A) indicate activity times.
B) show precedence relationships.
C) show activity start times.
D) show activity finish times.
The following questions employ the AON network and completed spreadsheet below.


A weakness of Gantt charts is that they do not explicitly
A) indicate activity times.
B) show precedence relationships.
C) show activity start times.
D) show activity finish times.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
22
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

What is the formula for the earliest finish time for activity i?
A) EFTi = ESTi + ti
B) EFTi = EFTj + tj
C) EFTi = EFTi−1 + ti
D) EFTi = ESTi − ti
The following questions employ the AON network and completed spreadsheet below.


What is the formula for the earliest finish time for activity i?
A) EFTi = ESTi + ti
B) EFTi = EFTj + tj
C) EFTi = EFTi−1 + ti
D) EFTi = ESTi − ti
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
23
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

Activities with zero slack
A) are dummy activities
B) belong to the critical path
C) must be completed first
D) must be delayed
The following questions employ the AON network and partial spreadsheet below.


Activities with zero slack
A) are dummy activities
B) belong to the critical path
C) must be completed first
D) must be delayed
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
24
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

The term "time zero" identifies
A) the start time for each activity.
B) the start time for the project.
C) midnight on each work day.
D) days with not wasted effort.
The following questions employ the AON network and completed spreadsheet below.


The term "time zero" identifies
A) the start time for each activity.
B) the start time for the project.
C) midnight on each work day.
D) days with not wasted effort.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
25
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

CPM and PERT differ because of
A) activity time estimates
B) cost calculations
C) precedence relationship
D) network diagram
The following questions employ the AON network and completed spreadsheet below.


CPM and PERT differ because of
A) activity time estimates
B) cost calculations
C) precedence relationship
D) network diagram
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
26
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Which of the following correctly describes the focus of the Critical Path Method (CPM)?
A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
The following questions employ the AON network and completed spreadsheet below.


Which of the following correctly describes the focus of the Critical Path Method (CPM)?
A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
27
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

The purpose of the backward pass in the Critical Path Method (CPM) technique is to
A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
The following questions employ the AON network and partial spreadsheet below.


The purpose of the backward pass in the Critical Path Method (CPM) technique is to
A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
28
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

A strength of Gantt charts is that they
A) clearly portray precedence relationships.
B) model uncertainty in activity duration times.
C) provide a timeline-based, graphical view of when activities can begin and end.
D) clearly identifies the critical path.
The following questions employ the AON network and completed spreadsheet below.


A strength of Gantt charts is that they
A) clearly portray precedence relationships.
B) model uncertainty in activity duration times.
C) provide a timeline-based, graphical view of when activities can begin and end.
D) clearly identifies the critical path.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
29
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

The critical path in PERT analysis is the path with the
A) smallest variance.
B) longest expected completion time.
C) smallest number of tasks.
D) smallest variance and longest expected completion time.
The following questions employ the AON network and completed spreadsheet below.


The critical path in PERT analysis is the path with the
A) smallest variance.
B) longest expected completion time.
C) smallest number of tasks.
D) smallest variance and longest expected completion time.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
30
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?
A) E2 + D2
B) MAX(IF(ISNUMBER(FIND($A$2:$A$8,C5)),$F$2:$F$8))
C) H2 − D2
D) MIN(IF(ISERR(FIND(A5,$C$5:$C$17)),MAX($F$5:$F$17),$G$5:$G$17))
The following questions employ the AON network and partial spreadsheet below.


Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?
A) E2 + D2
B) MAX(IF(ISNUMBER(FIND($A$2:$A$8,C5)),$F$2:$F$8))
C) H2 − D2
D) MIN(IF(ISERR(FIND(A5,$C$5:$C$17)),MAX($F$5:$F$17),$G$5:$G$17))
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
31
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

An activity
A) is an effort required to complete part of the project
B) is a milestone
C) consumes no resources
D) describes precedence relationship
The following questions employ the AON network and completed spreadsheet below.


An activity
A) is an effort required to complete part of the project
B) is a milestone
C) consumes no resources
D) describes precedence relationship
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
32
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Non-critical activities are distinguished by the presence of
A) positive slack.
B) idle resources.
C) wasted time.
D) zero slack.
The following questions employ the AON network and completed spreadsheet below.


Non-critical activities are distinguished by the presence of
A) positive slack.
B) idle resources.
C) wasted time.
D) zero slack.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
33
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

The longest path through a network is comprised of the ____ activities.
A) longest
B) essential
C) mandatory
D) critical
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


The longest path through a network is comprised of the ____ activities.
A) longest
B) essential
C) mandatory
D) critical
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
34
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

There are various similarities between the CPM and PERT methods. Which of the following is not one of those similarities?
A) Any project can be broken down into component activities that require different amounts of time.
B) Any project can be broken down into component activities that must be accomplished in a specific order.
C) Both techniques use the same method to calculate the time element of the activities in the project.
D) Both require a detailed network of the project that clearly indicates each of the main activities and the precedence relationship among the activities.
The following questions employ the AON network and completed spreadsheet below.


There are various similarities between the CPM and PERT methods. Which of the following is not one of those similarities?
A) Any project can be broken down into component activities that require different amounts of time.
B) Any project can be broken down into component activities that must be accomplished in a specific order.
C) Both techniques use the same method to calculate the time element of the activities in the project.
D) Both require a detailed network of the project that clearly indicates each of the main activities and the precedence relationship among the activities.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
35
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

For an activity with duration t, slack can be calculated as
A) LF-EF
B) LF-t
C) LS+t
D) LS+ES
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


For an activity with duration t, slack can be calculated as
A) LF-EF
B) LF-t
C) LS+t
D) LS+ES
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
36
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Refer to Exhibit 15.2. What formula is placed in cell G5 to calculate the Latest Start Time?
A) H5 − G5
B) F5 − G5
C) H5 − D5
D) F5 − D5
The following questions employ the AON network and completed spreadsheet below.


Refer to Exhibit 15.2. What formula is placed in cell G5 to calculate the Latest Start Time?
A) H5 − G5
B) F5 − G5
C) H5 − D5
D) F5 − D5
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
37
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

In a PERT network the time required to complete a path is a(n)
A) constant
B) random variable
C) Poisson distributed variable
D) exponentially distributed variable
The following questions employ the AON network and completed spreadsheet below.


In a PERT network the time required to complete a path is a(n)
A) constant
B) random variable
C) Poisson distributed variable
D) exponentially distributed variable
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
38
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

What is the earliest start time for activity D in the following diagram?
A) 3
B) 4
C) 6
D) 7
The following questions employ the AON network and completed spreadsheet below.


What is the earliest start time for activity D in the following diagram?

A) 3
B) 4
C) 6
D) 7
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
39
Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.

What are the immediate predecessors of activity D in this network?
A) A, B, C
B) B, C
C) E, F
D) E, G, H
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.


What are the immediate predecessors of activity D in this network?

A) A, B, C
B) B, C
C) E, F
D) E, G, H
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
40
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Which activities are critical in the following diagram?
A) A, C, D, F
B) B, D, E
C) A, C, D, E
D) A, B, D, E, F
The following questions employ the AON network and completed spreadsheet below.


Which activities are critical in the following diagram?

A) A, C, D, F
B) B, D, E
C) A, C, D, E
D) A, B, D, E, F
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
41
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

In project control charts, the horizontal bars are shaded to indicate
A) work completed
B) work to be completed
C) overcapacity
D) undercapacity
The following questions employ the AON network and partial spreadsheet below.


In project control charts, the horizontal bars are shaded to indicate
A) work completed
B) work to be completed
C) overcapacity
D) undercapacity
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
42
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT)?
A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
The following questions employ the AON network and partial spreadsheet below.


Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT)?
A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
43
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Shortening the activity completion time is called
A) expediting
B) speeding
C) accelerating
D) crashing
The following questions employ the AON network and completed spreadsheet below.


Shortening the activity completion time is called
A) expediting
B) speeding
C) accelerating
D) crashing
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
44
How many paths are there in the following project precedence network?
A) 6
B) 7
C) 8
D) 9

A) 6
B) 7
C) 8
D) 9
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
45
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?
A) E2 + D2
B) MAX(IF(ISERR(FIND($A$5:$A$17,C5)),0,$F$5:$F$17))
C) H2 − D2
D) MIN(IF(ISNUMBER(FIND(A5,$C$2:$C$8)),$G$2:$G$8))
The following questions employ the AON network and partial spreadsheet below.


Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?
A) E2 + D2
B) MAX(IF(ISERR(FIND($A$5:$A$17,C5)),0,$F$5:$F$17))
C) H2 − D2
D) MIN(IF(ISNUMBER(FIND(A5,$C$2:$C$8)),$G$2:$G$8))
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
46
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

What is the latest finish time for activity D in the following diagram?
A) 6
B) 13
C) 14
D) 15
The following questions employ the AON network and partial spreadsheet below.


What is the latest finish time for activity D in the following diagram?

A) 6
B) 13
C) 14
D) 15
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
47
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Critical activities are distinguished by the presence of
A) slack.
B) idle resources.
C) wasted time.
D) zero slack.
The following questions employ the AON network and completed spreadsheet below.


Critical activities are distinguished by the presence of
A) slack.
B) idle resources.
C) wasted time.
D) zero slack.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
48
The critical path is the ____ path throughout the network.
A) longest
B) most expensive
C) shortest
D) least expensive
A) longest
B) most expensive
C) shortest
D) least expensive
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
49
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Which of the following definitions correctly defines the acronym, PERT?
A) Program Evaluation and Review Technique.
B) Process Evaluation and Review Technique.
C) Program Evaluation and Reduction Technique.
D) Program Explanation and Reduction Technique.
The following questions employ the AON network and completed spreadsheet below.


Which of the following definitions correctly defines the acronym, PERT?
A) Program Evaluation and Review Technique.
B) Process Evaluation and Review Technique.
C) Program Evaluation and Reduction Technique.
D) Program Explanation and Reduction Technique.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
50
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

Activity-on-Arc (AOA) networks do not allow multiple arcs with common start and finish nodes. If this must be represented, how is an AOA network modified?
A) The network is redrawn into an Activity-on-Node network.
B) Connect the arcs to the node using an IFERROR() function.
C) Phantom (dummy) activity arcs are added.
D) Zero duration activity arcs are added.
The following questions employ the AON network and partial spreadsheet below.


Activity-on-Arc (AOA) networks do not allow multiple arcs with common start and finish nodes. If this must be represented, how is an AOA network modified?
A) The network is redrawn into an Activity-on-Node network.
B) Connect the arcs to the node using an IFERROR() function.
C) Phantom (dummy) activity arcs are added.
D) Zero duration activity arcs are added.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
51
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

A project plan is established
A) before project activities begin and is modified as time goes on and conditions change
B) before project activities begin
C) before project organization
D) dynamically, as conditions change
The following questions employ the AON network and partial spreadsheet below.


A project plan is established
A) before project activities begin and is modified as time goes on and conditions change
B) before project activities begin
C) before project organization
D) dynamically, as conditions change
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
52
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

For an activity with duration t, slack can be calculated as
A) LS-ES
B) LF-t
C) LS+t
D) LS+ES
The following questions employ the AON network and partial spreadsheet below.


For an activity with duration t, slack can be calculated as
A) LS-ES
B) LF-t
C) LS+t
D) LS+ES
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
53
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

Slack represents the amount of time by which an activity can be delayed without delaying the entire project, assuming that
A) all successor activities start at their earliest start times.
B) all predecessor activities start at their earliest start times.
C) immediate predecessor activities start at their earliest start times.
D) all predecessor activities start at their latest start times.
The following questions employ the AON network and partial spreadsheet below.


Slack represents the amount of time by which an activity can be delayed without delaying the entire project, assuming that
A) all successor activities start at their earliest start times.
B) all predecessor activities start at their earliest start times.
C) immediate predecessor activities start at their earliest start times.
D) all predecessor activities start at their latest start times.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
54
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

What is the correct formula to compute the variance of an activity using PERT?
A)
B)
C)
D)
The following questions employ the AON network and completed spreadsheet below.


What is the correct formula to compute the variance of an activity using PERT?
A)

B)

C)

D)

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
55
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Slack for activity I is computed as
A) LFTi − ESTi
B) LSTi − ESTi
C) ESTi − LSTi
D) EFTi − LFTi
The following questions employ the AON network and completed spreadsheet below.


Slack for activity I is computed as
A) LFTi − ESTi
B) LSTi − ESTi
C) ESTi − LSTi
D) EFTi − LFTi
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
56
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

What formula should go in cell I5 of the following spreadsheet to compute Actual Time Between Starts?
A) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3)
B) =VLOOKUP(H5,$B$5:$D$11,2)-VLOOKUP(G5,$B$5:$D$11,2)
C) =VLOOKUP(G5,$B$5:$D$11,3)-VLOOKUP(H5,$B$5:$D$11,3)
D) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,2)
The following questions employ the AON network and partial spreadsheet below.


What formula should go in cell I5 of the following spreadsheet to compute Actual Time Between Starts?

A) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3)
B) =VLOOKUP(H5,$B$5:$D$11,2)-VLOOKUP(G5,$B$5:$D$11,2)
C) =VLOOKUP(G5,$B$5:$D$11,3)-VLOOKUP(H5,$B$5:$D$11,3)
D) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,2)
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
57
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?
A) Activity A
B) Activity C
C) Activity D
D) Activity G
The following questions employ the AON network and completed spreadsheet below.


Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?
A) Activity A
B) Activity C
C) Activity D
D) Activity G
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
58
If we are employing Activity-On-Arc (AOA) network design, the arcs in the network diagram represent
A) significance relationships.
B) precedence relationships.
C) tasks to complete.
D) task times.
A) significance relationships.
B) precedence relationships.
C) tasks to complete.
D) task times.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
59
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.

Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?
A) E, F
B) B
C) C
D) B, C
The following questions employ the AON network and partial spreadsheet below.


Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?
A) E, F
B) B
C) C
D) B, C
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
60
One of PERT's bold assumptions is that
A) individual activity times are independent of each other.
B) individual activity times are dependent of each other.
C) individual activity times are constant.
D) individual activity times can be added together.
A) individual activity times are independent of each other.
B) individual activity times are dependent of each other.
C) individual activity times are constant.
D) individual activity times can be added together.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
61
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.

Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.


Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
62
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
63
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.4. Identify each path through the network and its expected length.
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.4. Identify each path through the network and its expected length.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
64
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
65
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
66
What are the immediate successors of activity D in this network?
A) A, B, C
B) B, C
C) E, F
D) E

A) A, B, C
B) B, C
C) E, F
D) E
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
67
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
68
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.3. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.3. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
69
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?
The following questions use the information below.
Consider the CPM network for the following set of activities:

Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
70
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.3. Identify each path through the network and its expected length.
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.3. Identify each path through the network and its expected length.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
71
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
72
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
73
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
74
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
75
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
76
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.
The following questions use the information below.
Consider the CPM network for the following set of activities:

Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
77
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.

Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.


Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
78
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
79
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:

Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?

Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck
80
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.

Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.


Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?
Unlock Deck
Unlock for access to all 82 flashcards in this deck.
Unlock Deck
k this deck